The following table gives the baseline cost and time estimates (BCE and BTE), the cost...

90.2K

Verified Solution

Question

Accounting

The following table gives the baseline cost and time estimates (BCE and BTE), the cost and time estimates to correct for failure, and the likelihood of failure for each work package.

image

What is the project expected cost (EC) and expected time (ET)?

Q. 5 The following table gives the baseline cost and time estimates (BCE and BTE), the cost and time estimates to correct for failure, and the likelihood of failure for each work package. Corrective WBS BCE BTE(WK) Cost Time Likelihood Element L $20,000 9 $4000 2 .2 V $16,000 8 $4000 2 .3 T $32,000 5 $8000 2 1 U $20,000 7 $12,000 3 .2 S $16,000 3 $4000 1 .3 J $18,000 3 $4000 1 1 R $10,000 4 $4000 3 .3 $15,000 6 $5000 2 3 What is the project expected cost (EC) and expected time (ET)

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students