The following represents a project with known activity times. All times are in week Predecessors...

70.2K

Verified Solution

Question

Accounting

image

The following represents a project with known activity times. All times are in week Predecessors Time 16 12 Activity B D E 8 B 28 16 C,D E F 20 What is the estimated time to complete the project? O a. 56 weeks O b. 76 weeks c. 100 weeks Od. 60 weeks

Answer & Explanation Solved by verified expert