The following information is providedabout a training and development project.
Activity | Duration (weeks) | Preceding Activities |
A | 3 | None |
B | 5 | None |
C | 14 | A |
D | 5 | A |
E | 4 | B |
F | 7 | B |
G | 8 | D, E |
H | 5 | G, F |
(a) Drawthe PDM/CPM diagram, complete with forward and backward passinformation. Find the critical path.
[12 marks]
(b) AssumeActivity A (hire trainers) took 5 weeks. Draw the PDM/CPM diagramagain.[7 marks]
(c) From whichactivity would you suggest transferring resources, and to whatactivity, so that the original target training date may bemaintained?[6 marks]
[Total 25 marks]