The following has been received as a result of bids.

17. An RFP was issued for business training in an officeenvironment. As a result, seven proposals were received. Thesubsequent rated and price evaluations for the firms are below.

Firm                            RatedEvaluation                   Financial Bid

A                                            90                               $150.000

B                                           85                               $140,000

C                                            80                               $120,000

D                                            75                               $110,000

E                                             70                               $120,000

F                                             65                               $119,000

G                                            60                               $100,000               

The evaluated pass mark for this requirement was 70

1. Which firm would be recommended to be awarded the contract ifthe method of evaluation is the lowest priced responsive(technically compliant) proposal?

2. Which firm would be recommended to be awarded the contract ifthe method of evaluation is the lowest priced responsive(technically compliant) proposal and there was a stipulated maximumfinancial budget of $139,000?

3. Which firm would be recommended to be awarded the contract ifthe method of evaluation is lowest price per point?

4. Which firm would be recommended to be awarded the contract ifthe method of evaluation is highest combined rating with price at50% and rated evaluation 50% of the total?

5. Which firm would be recommended to be awarded the contract ifthe method of evaluation is highest combined rating with price at25% and rated evaluation 75% of the total?

Note: you MUST show any calculations.

Answer & Explanation Solved by verified expert
3.8 Ratings (397 Votes)
1 technically compliant means F and G are out of the picture Out of what remain the lowest priced is D with a bid of 110000 2 technically compliant means F and G are out of the picture Out of what remain    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students