The following four months of data were collected on utility cost and the number of...

90.2K

Verified Solution

Question

Accounting

The following four months of data were collected on utility cost and the number of labor hours in a factory.

Month Utility cost

Labor hours

January $115,550 7,540

February 106,782 6,900

March 105,400 6,840

April 110,112 7,150

What would be the estimate of electricity cost if the factory incurred 7,250 labor hours next month?