The following data relate to direct labor costs for the current period:

Standard costs 7,100 hours at $11.60
Actual costs 6,100 hours at $10.60

What is the direct labor time variance?

a.$11,600 unfavorable

b.$10,600 favorable

c.$10,600 unfavorable

d.$11,600 favorable