The following data is given for the Stringer Company: Budgeted production 900...

80.2K

Verified Solution

Question

Accounting

The following data is given for the Stringer Company:

Budgeted production 900 units
Actual production 1,056 units
Materials:
Standard price per ounce $1.9
Standard ounces per completed unit 12
Actual ounces purchased and used in production 13,052
Actual price paid for materials $26,757
Labor:
Standard hourly labor rate $14.30 per hour
Standard hours allowed per completed unit 5.0
Actual labor hours worked 5,438.4
Actual total labor costs $82,936
Overhead:
Actual and budgeted fixed overhead $1,153,000
Standard variable overhead rate $28.00 per standard labor hour
Actual variable overhead costs $152,275
Overhead is applied on standard labor hours.

The direct materials quantity variance is

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students