The following costs have been estimated for the activities in a project: ...

50.1K

Verified Solution

Question

Accounting

The following costs have been estimated for the activities in a project:

ACTIVITY

IMMEDIATE PREDECESSORS

TIME

TOTAL COST ($)

A

-

10

11600

B

-

6

14400

C

A

5

5700

D

B

8

15200

E

C, D

9

8910

F

C, D

7

14000

G

F

5

5500

A. Develop a cost budgeted schedule based on the earliest start time like Table 6 on page 8 in the notes. Please keep one decimal place.

B. Develop a cost budgeted schedule based on the latest start time like Table 7 on page 8 in the notes. Please keep one decimal place.

Budgeted Costs, Using Earliest Start Times
Table 6 Page 8 Week
Activity 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Total
A 11 11 22
B 10 10 10 30
C 13 13 26
D 12 12 12 12 48
E 14 14 14 14 56
F 10 10 10 30
G 16 16 16 16 16 80
H 8 8 16
308
Total per week 21 21 23 25 36 36 36 14 16 16 16 16 16 8 8
Total to date 21 42 65 90 126 162 198 212 228 244 260 276 292 300 308
Budgeted Costs Using Latest Start Times
Table 7 Page 8 Week
Activity 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Total
A 11 11 22
B 10 10 10 30
C 13 13 26
D 12 12 12 12 48
E 14 14 14 14 56
F 10 10 10 30
G 16 16 16 16 16 80
H 8 8 16
308
Total per week 11 21 23 23 26 26 26 26 16 16 26 26 26 8 8
Total to date 11 32 55 78 104 130 156 182 198 214 240 266 292 300 308

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students