The following activities are part of a project to be scheduled using CPM: a. What is the critical path? A-B-D-F-GA-C-D-F-GA-C-D-E-GA-B-E-G b. How many weeks will it take to complete the project? b. How many weeks will it take to complete the project? c. How much slack does activity B have