The Evanstonian is an upscale independent hotel that caters toboth business and leisure travelers. When a guest calls roomservice at The Evanstonian, the room-service manager takes down theorder. The service manager then submits an order ticket to thekitchen to begin preparing the food. She also gives an order to thesommelier (i.e., the wine waiter) to fetch wine from the cellar andto prepare any other alcoholic beverages. Finally, she assigns theorder to a waiter.

  It takes 6 minutes to take down the order and toassign the work to the kitchen, sommelier, and waiter. It takes thekitchen 16 minutes to prepare the typical order. It takes thesommelier 8 minutes to prepare the drinks for the order. While thekitchen and the sommelier are doing their tasks, the waiter readiesa cart (i.e., puts a tablecloth on the cart and gatherssilverware). This takes 8 minutes per order.

  Once the food, wine, and cart are ready, the waiterdelivers it to the guest’s room. It takes the waiter 14 minutes todeliver the meal to the customer. It takes the waiter additional 2minutes to return to the station and debit the guest’ account. Allthe times mentioned represent flow time at the various activities,an include the effects of waiting.

Activity Time and Visit

Activity

Activity Time

Visit

to take down the order and to assign the work to the kitchen

to prepare the typical order

to prepare the drinks for the order

waiter readies a cart

to deliver the meal to the customer

to return to the station and debit the guest’ account

6

16

8

8

14

2

2

1

1

1.5

1

2

a. Draw a process map for the room-service process: from receiptof order to delivery of food

b. What is the critical path and theoretical flow time of theprocess?

c. What is the effect on the process flow time if the waitercould prepare the cart in 6 minutes, instead of 8?

d. Computes the waste time due to rework?

e. The hotel wants to reduce its theoretical flow time by 4minutes. Give an example of using elimination approach to reducethe theoretical flow time. (Show which activity or activitiesshould be reduced and by how many minutes).

Answer & Explanation Solved by verified expert
3.6 Ratings (352 Votes)
a Draw a process map for the roomservice processfrom receipt of order to delivery of foodAnswerPlease see below diagrama What is the critical path and theoretical flowtime of    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students