. The contract indicated only silty and blue clays and a smallamount of shale would be encountered on the site. A large quantityof shale was actually encountered instead of the silty and claymaterial. The contractor had intended to use the excavated materialof silt and clay for fill at another location on the job, however,the excavated material would not compact well and the contractorhad to purchase fill from another source at a cost of $40,000. Isthe contractor entitled to damages of $40,000 from the owner? a.Applicable rule: b. Your analysis:

Answer & Explanation Solved by verified expert
4.0 Ratings (646 Votes)
A Applicable rule here is that whatever the contract states the material should have been exactly the same Any deviation from a contract can be entitled to payments that can be filed    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students