The boxes on the network represent tasks where the top item in each box is...
50.1K
Verified Solution
Question
Finance
The boxes on the network represent tasks where the top item in each box is the task name (i.e. A-1), the middle item is the resource (i.e. Magenta), and the bottom item is the task duration in days. The task durations have already been cut by 50%.
a) Lay out the Critical Chain schedule for this project. You will first need to lay out the project network. You may use Microsoft Project, Excel, PowerPoint, or any other tool that allows you to draw the network. A hand drawn view of the project network for each step is okay if you dont have a tool you can easily use. Start the project on March 1, 2021. What is the project end date before leveling any resource conflicts? What is the project end date after leveling resources?
b) Identify the critical chain.
c) Lastly, size and insert the project and feeding buffers. Be sure to identify the approach you used for sizing the buffers. What is the project end date after inserting the appropriate buffers?
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
- Unlimited Question Access with detailed Answers
- Zin AI - 3 Million Words
- 10 Dall-E 3 Images
- 20 Plot Generations
- Conversation with Dialogue Memory
- No Ads, Ever!
- Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Other questions asked by students
StudyZin's Question Purchase
1 Answer
$0.99
(Save $1 )
One time Pay
- No Ads
- Answer to 1 Question
- Get free Zin AI - 50 Thousand Words per Month
Unlimited
$4.99*
(Save $5 )
Billed Monthly
- No Ads
- Answers to Unlimited Questions
- Get free Zin AI - 3 Million Words per Month
*First month only
Free
$0
- Get this answer for free!
- Sign up now to unlock the answer instantly
You can see the logs in the Dashboard.