The Beatles Co. began construction of a recording studio on January 1, 2020 and completed...

90.2K

Verified Solution

Question

Accounting

The Beatles Co. began construction of a recording studio on January 1, 2020 and completed the studio on October 31, 2021. The details on the expenditures relating to the project were as follows:

January 1, 2020

March 31, 2020

October 1, 2020

February 1, 2021

April 30, 2021

$ 1,400,000

2,700,000

900,000

1,800,000

1,500,000

The company provided the following information on its various debts outstanding during the entire period of the construction:

12%, ten-year note issued on December 31, 2012 1,000,000

9%, five-year bank loan taken on January 1, 2019 2,000,000

The capitalzied cost of the recording studio on Beatles' balance sheet after October 31, 2021 was:

Multiple Choice

  • a-$8,665,000.

  • b-$8,300,000.

  • c-$8,900,000.

  • d-$9,453,500.

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students