The ABC Manufacturing Co. has made a decision to replace an existing production line with new...

50.1K

Verified Solution

Question

Operations Management

The ABC Manufacturing Co. has made a decision to replace anexisting production line with new equipment. This project willrequire several tasks (jobs) with precedence relationships andduration (weeks) as shown in the following table. The project willbe finished when activities A-J are all finished.

Activity

Predecessors

Duration (Weeks)

A

—

5

B

—

5

C

A

11

D

B

9

E

C

4

F

C, D

10

G

E

4

H

G

3

I

G

4

J

F, H

3

a)       Create anActivity-On-Node network diagram for this Project.

b)       Calculate the earlieststart (ES) and finish (EF) times and latest start (LS) and finish(LF) times, the total slack (TS) and free slack (FS) for each ofthe activities in the network.

c)       Identify the criticalpath(s).

d)       What is the projectcompletion duration?

Answer & Explanation Solved by verified expert
3.8 Ratings (368 Votes)
ActivitiyPredeccorsDurationESEFLSLFTotal SlackFree    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students