The 500 MW coal steam power plant will be built from the beginning of 2019...

60.1K

Verified Solution

Question

Finance

The 500 MW coal steam power plant will be built from the beginning of 2019 at a cost of Rp 20 trillion. The construction period is 4 years with the time schedule of cash flow for construction cost as follow: 20% of the cost at the beginning of 2019, 40% of the cost at the beginning of 2020, 30% of the cost at the beginning of 2021, and 10% of the cost at the beginning of 2022. Stable electricity production will begin at the beginning of 2024, and revenue from electricity sales prices will be obtained at the end of each year. Operating time is 24 hours / day and 340 days per year, because the 25 days are used for maintenance. Capasity factor is 80%. Bank loan interest is 12% / year. If you want the investment cost to be Rp 696 / KWh, the question: a) make the cash flow digram, b) calculate the pay back period for how many years?

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students