The 2nd unit of a 10-unit job took eight hours to complete. The 6th unit...

90.2K

Verified Solution

Question

Finance

image
The 2nd unit of a 10-unit job took eight hours to complete. The 6th unit has been worked on for two hours, but is not yet finished. Estimate the additional amount of time needed to finish the 6th unit if the work has a Box learning curve slope O a. 6.143 hours O b.3.617 hours O C.4.143 hours od 3.058 hours e. 5.114 hours munding is continuous

Answer & Explanation Solved by verified expert