Question

Accounting

\table[[ELEMENT,OBSERVATIONS (MINUTES),\table[[PERFORMANCE],[RATING (%)]]],[1,2,3,4,5],[Prepare daily reports,35,40,33,42,39,120],[Photocopy results,12,10,36,15,13,110],[\table[[Label and package],[reports]],3,3,5,5,4,90],[Distribute reports,15,18,21,17,45,85]]
a. Compute the normal time for each work element.
b. If the allo sance for this type of work is 15%, what is the standard time?

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students