Sunny Park Tailors has been asked to make three different types of wedding suits for separate...

80.2K

Verified Solution

Question

General Management

Sunny Park Tailors has been asked to make three different typesof wedding suits for separate customers. The table below highlightsthe time taken in hours for cutting and sewing? (process 1) anddelivery? (process 2) of each of the suits.

??

Times Taken for Different Activities (hours)

Suit Cut and Sew Deliver

1 7 2

2 4 3

3 5 6

???????????????

For the schedule developed using the? Johnson's rule, the totallength of time taken to complete the three suits? (includingdelivery)? =

Of the two developed? schedules, which rule gets the schedulefinished sooner.??????????????????????????

Answer & Explanation Solved by verified expert
3.7 Ratings (722 Votes)
As per Johnsons rule follow the following steps to determinethe sequence1 Step 1 Choose the suit with least time in either of the 2stages of processes Thats Suit 1 with least time as 2 hours    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students