Standard Quantities of Labor and Materials Stillwater Designs rebuilds defective units of its S12L7 Kicker...

50.1K

Verified Solution

Question

Accounting

Standard Quantities of Labor and Materials

Stillwater Designs rebuilds defective units of its S12L7 Kicker speaker model. During the year, Stillwater rebuilt 7,500 units. Materials and labor standards for performing the repairs are as follows:

Direct materials (1 recon kit @ $160) $160
Direct materials (1 cabinet @ $50) 50
Direct labor (3 hrs. @ $14) 42

Required:

1. Compute the standard hours allowed for a volume of 7,500 rebuilt units. hours

2. Compute the standard number of kits and cabinets allowed for a volume of 7,500 rebuilt units.

Standard number of kits: kits
Standard number of cabinets: cabinets

3. Suppose that during the first month of the year, 4,250 standard hours were allowed for the units rebuilt. How many units were rebuilt during the first month? Round your answer to the nearest whole unit. units

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students