Standard Product Cost Sana Rosa Company manufactures unfinished home furniture. Sana Rosa uses a standard...

70.2K

Verified Solution

Question

Accounting

Standard Product Cost

Sana Rosa Company manufactures unfinished home furniture. Sana Rosa uses a standard cost system. The direct labor, direct materials, and factory overhead standards for an unfinished dining room table are as follows:

Direct labor: standard rate $21 per hr.
standard time per unit 2 hrs.
Direct materials (oak): standard price $8 per bd. ft.
standard quantity 17 bd. ft.
Variable factory overhead: standard rate $3.2 per direct labor hr.
Fixed factory overhead: standard rate $1.2 per direct labor hr.

a. Determine the standard cost per dining room table. If required, round your answer to two decimal places. $per table

b. A standard cost system provides Sana Rosa management a cost control tool using the principle of . Using this principle, cost deviations from standards can be investigated and corrected.

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students