Standard Cost per Unit Actual Cost per Unit ...

90.2K

Verified Solution

Question

Accounting

Standard Cost per Unit Actual Cost per Unit
Direct materials:
Standard: 1.80 feet at $2.60 per foot $

4.68

Actual: 1.75 feet at $2.80 per foot $ 4.90
Direct labor:
Standard: 0.90 hours at $16.00 per hour

14.40

Actual: 0.95 hours at $15.40 per hour 14.63
Variable overhead:
Standard: 0.90 hours at $7.40 per hour 6.66
Actual: 0.95 hours at $7.00 per hour 6.65
Total cost per unit $

25.74

$ 26.18
Excess of actual cost over standard cost per unit $ 0.44

The production superintendent was pleased when he saw this report and commented: This $0.44 excess cost is well within the 5 percent limit management has set for acceptable variances. It's obvious that there's not much to worry about with this product."

Actual production for the month was 14,000 units. Variable overhead cost is assigned to products on the basis of direct labor-hours. There were no beginning or ending inventories of materials.

Required:

1. Compute the following variances for May:

1a. Materials price variance
Materials quantity variance
1b. Labor rate variance
Labor efficiency variance
1c. Variable overhead rate variance
Variable overhead efficiency variance

2. How much of the $0.44 excess unit cost is traceable to each of the variances computed in (1) above.

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students