Stainless Steel spoons are tested after manufacture with each test taking 10 minutes. If the plant...

90.2K

Verified Solution

Question

Mechanical Engineering

Stainless Steel spoons are tested after manufacture with eachtest taking 10 minutes. If the plant makes 200,000 units a day andthe quality Page 117-Sep-2018 assurance technologist recommendstesting 1% of them to failure, is this sampling plan sensible? Whatwould you recommend? Why?

Answer & Explanation Solved by verified expert
4.5 Ratings (666 Votes)
A technologist can work not more than 8 hours a day In one day he can check upto 8x6010 48 samples 1 of 200000 becomes 2000 samples It is required more than 40 sample tester to accomplish the target of 1 My recommendation would    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students