Splish Construction Company uses the percentage-of-completion method of accounting. In 2020, Splish began work under contract #E2-D2, which provided for a contract price of $2,170,000. Other details follow:
2020 | 2021 | |||
Costs incurred during the year | $615,810 | $1,422,000 | ||
Estimated costs to complete, as of December 31 | 963,190 | 0 | ||
Billings during the year | 426,000 | 2,170,000 | ||
Collections during the year | 343,000 | 1,520,000 |
(a)
What portion of the total contract price would be recognized as revenue in 2020? In 2021?
Revenue recognized in 2020 | $ | |
Revenue recognized in 2021 | $ |
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
- Unlimited Question Access with detailed Answers
- Zin AI - 3 Million Words
- 10 Dall-E 3 Images
- 20 Plot Generations
- Conversation with Dialogue Memory
- No Ads, Ever!
- Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Other questions asked by students
StudyZin's Question Purchase
1 Answer
$0.99
(Save $1 )
One time Pay
- No Ads
- Answer to 1 Question
- Get free Zin AI - 50 Thousand Words per Month
Best
Unlimited
$4.99*
(Save $5 )
Billed Monthly
- No Ads
- Answers to Unlimited Questions
- Get free Zin AI - 3 Million Words per Month
*First month only
Free
$0
- Get this answer for free!
- Sign up now to unlock the answer instantly
You can see the logs in the Dashboard.