Sandhill Construction Company has entered into a non-cancellable contract beginning January 1, 2020, to build...

50.1K

Verified Solution

Question

Accounting

image

Sandhill Construction Company has entered into a non-cancellable contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $650,000 and will take three years to construct. The complex will be billed to the purchasing company at $905,000. The following data pertain to the construction period. 2022 $660,000 Costs to date Estimated costs to complete Progress billings to date (non-refundable) Cash collected to date 2020 $292,500 357,500 292,500 262,500 2021 $487,500 162,500 600,000 550,000 905,000 905,000 Using the percentage-of-completion method, calculate the estimated gross profit that would be recognized during each year of the construction period. (Enter negative amounts using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45).) 2020 2021 2022 Gross profit / (loss) $ SHOW LIST OF ACCOUNTS LINK TO TEXT Using the completed-contract method, calculate the estimated gross profit that would be recognized during each year of the construction period. (Do not leave any answer field blank. Enter O for amounts. Enter negative amounts using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45).) 2020 2021 2022 Gross profit / (loss) $

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students