Samtech Manufacturing purchased land and building for $4 million. In addition to the purchase price, Samtech...

90.2K

Verified Solution

Question

Accounting

Samtech Manufacturing purchased land and building for $4million. In addition to the purchase price, Samtech made thefollowing expenditures in connection with the purchase of the landand building:

Title insurance$34,000
Legal fees for drawing the contract9,000
Pro-rated property taxes for the period after acquisition54,000
State transfer fees5,800


An independent appraisal estimated the fair values of the land andbuilding, if purchased separately, at $3.5 and $1.5 million,respectively. Shortly after acquisition, Samtech spent $100,000 toconstruct a parking lot and $58,000 for landscaping.

Required:
1. Determine the initial valuation of each assetSamtech acquired in these transactions.
2. Determine the initial valuation of each asset,assuming that immediately after acquisition, Samtech demolished thebuilding. Demolition costs were $430,000 and the salvaged materialswere sold for $6,500. In addition, Samtech spent $97,000 clearingand grading the land in preparation for the construction of a newbuilding.
  

Answer & Explanation Solved by verified expert
3.9 Ratings (767 Votes)
Part 1 Cost of Land and Building Purchase Price 4000000 Title search and insurance 34000 Legal Fees 9000 State Transfer Fees 5800 Total Cost Land and    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students