Risk classes and RADR ??Moses Manufacturing is attempting to select the best of three mutually exclusive?...

90.2K

Verified Solution

Question

Finance

Risk classes and RADR ??Moses Manufacturing is attempting toselect the best of three mutually exclusive? projects, X,? Y, andZ. Although all the projects have

55?-year

?lives, they possess differing degrees of risk. Project X is inclass?V, the? highest-risk class; project Y is in class? II, the?below-average-risk class; and project Z is in class? III, the?average-risk class. The basic cash flow data for each project andthe risk classes and? risk-adjusted discount rates? (RADRs) used bythe firm are shown in the following tables

LOADING...

.

a. Find the ?risk-adjusted NPV for each project.

b. Which? project, if? any, would you recommend that the firm?undertake?

Project X

Project Y

Project Z

Initial investment

?(CF 0CF0?)

?$177 comma 000177,000

?$239 comma 000239,000

?$305 comma 000305,000

Year

?(tt ?)

Cash inflows

?(CF Subscript tCFt?)

1

?$85 comma 00085,000

?$59 comma 00059,000

?$92 comma 00092,000

2

??67 comma 00067,000

??65 comma 00065,000

??92 comma 00092,000

3

??61 comma 00061,000

??76 comma 00076,000

??92 comma 00092,000

4

??63 comma 00063,000

??83 comma 00083,000

??92 comma 00092,000

5

??58 comma 00058,000

??91 comma 00091,000

??92 comma 00092,000

Risk Classes and RADRs

Risk Class

Description

Risk adjusted discount rate? (RADR)

I

Lowest risk

10.7 %

II

?Below-average risk

13.8

III

Average risk

15.7

IV

?Above-average risk

19.6

V

Highest risk

22.7

Answer & Explanation Solved by verified expert
3.7 Ratings (469 Votes)
1Project XYearcash flowpresent value of cash flow cash flow1rn r 227present value of cash flow cash flow1rn r    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Transcribed Image Text

Risk classes and RADR ??Moses Manufacturing is attempting toselect the best of three mutually exclusive? projects, X,? Y, andZ. Although all the projects have55?-year?lives, they possess differing degrees of risk. Project X is inclass?V, the? highest-risk class; project Y is in class? II, the?below-average-risk class; and project Z is in class? III, the?average-risk class. The basic cash flow data for each project andthe risk classes and? risk-adjusted discount rates? (RADRs) used bythe firm are shown in the following tablesLOADING....a. Find the ?risk-adjusted NPV for each project.b. Which? project, if? any, would you recommend that the firm?undertake?Project XProject YProject ZInitial investment?(CF 0CF0?)?$177 comma 000177,000?$239 comma 000239,000?$305 comma 000305,000Year?(tt ?)Cash inflows?(CF Subscript tCFt?)1?$85 comma 00085,000?$59 comma 00059,000?$92 comma 00092,0002??67 comma 00067,000??65 comma 00065,000??92 comma 00092,0003??61 comma 00061,000??76 comma 00076,000??92 comma 00092,0004??63 comma 00063,000??83 comma 00083,000??92 comma 00092,0005??58 comma 00058,000??91 comma 00091,000??92 comma 00092,000Risk Classes and RADRsRisk ClassDescriptionRisk adjusted discount rate? (RADR)ILowest risk10.7 %II?Below-average risk13.8IIIAverage risk15.7IV?Above-average risk19.6VHighest risk22.7

Other questions asked by students