Question

Accounting

Required information

[The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows:

Find the Revenue and Gross Profit for the three years

2018 2019 2020
Cost incurred during the year $ 2,072,000 $ 2,738,000 $ 2,849,000
Estimated costs to complete as of year-end 5,328,000 2,590,000 0
Billings during the year 2,160,000 2,650,000 5,190,000
Cash collections during the year 1,880,000 2,700,000 5,420,000

Westgate recognizes revenue over time according to percentage of completion.

rev: 09_15_2017_QC_CS-99734

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students