Required information [The following information applies to the questions displayed below.] Antuan Company...
90.2K
Verified Solution
Question
Accounting
Required information
[The following information applies to the questions displayed below.] Antuan Company set the following standard costs for one unit of its product.
Direct materials (3.0 Ibs. @ $6.00 per Ib.) | $ | 18.00 |
Direct labor (2.0 hrs. @ $10.00 per hr.) | 20.00 | |
Overhead (2.0 hrs. @ $18.50 per hr.) | 37.00 | |
Total standard cost | $ | 75.00 |
The predetermined overhead rate ($18.50 per direct labor hour) is based on an expected volume of 75% of the factorys capacity of 20,000 units per month. Following are the companys budgeted overhead costs per month at the 75% capacity level.
Overhead Budget (75% Capacity) | |||||
Variable overhead costs | |||||
Indirect materials | $ | 15,000 | |||
Indirect labor | 75,000 | ||||
Power | 15,000 | ||||
Repairs and maintenance | 30,000 | ||||
Total variable overhead costs | $ | 135,000 | |||
Fixed overhead costs | |||||
DepreciationBuilding | 24,000 | ||||
DepreciationMachinery | 72,000 | ||||
Taxes and insurance | 17,000 | ||||
Supervision | 307,000 | ||||
Total fixed overhead costs | 420,000 | ||||
Total overhead costs | $ | 555,000 | |||
The company incurred the following actual costs when it operated at 75% of capacity in October.
Direct materials (45,500 Ibs. @ $6.20 per lb.) | $ | 282,100 | |||
Direct labor (21,000 hrs. @ $10.20 per hr.) | 214,200 | ||||
Overhead costs | |||||
Indirect materials | $ | 41,950 | |||
Indirect labor | 176,850 | ||||
Power | 17,250 | ||||
Repairs and maintenance | 34,500 | ||||
DepreciationBuilding | 24,000 | ||||
DepreciationMachinery | 97,200 | ||||
Taxes and insurance | 15,300 | ||||
Supervision | 307,000 | 714,050 | |||
Total costs | $ | 1,210,350 | |||
rev: 03_28_2018_QC_CS-122864
3. Compute the direct materials cost variance, including its price and quantity variances. AQ = Actual Quantity SQ = Standard Quantity AP = Actual Price SP = Standard Price
4. Compute the direct labor cost variance, including its rate and efficiency variances. AH = Actual Hours SH = Standard Hours AR = Actual Rate SR = Standard Rate
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
- Unlimited Question Access with detailed Answers
- Zin AI - 3 Million Words
- 10 Dall-E 3 Images
- 20 Plot Generations
- Conversation with Dialogue Memory
- No Ads, Ever!
- Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Other questions asked by students
StudyZin's Question Purchase
1 Answer
$0.99
(Save $1 )
One time Pay
- No Ads
- Answer to 1 Question
- Get free Zin AI - 50 Thousand Words per Month
Unlimited
$4.99*
(Save $5 )
Billed Monthly
- No Ads
- Answers to Unlimited Questions
- Get free Zin AI - 3 Million Words per Month
*First month only
Free
$0
- Get this answer for free!
- Sign up now to unlock the answer instantly
You can see the logs in the Dashboard.