Reed Corp. has set the following standard direct materials and direct labor costs per unit for the product it manufactures.
Direct materials (15 lbs. @ $3 per lb.)
$45
Direct labor (4 hrs. @ $14 per hr.)
56
During June the company incurred the following actual costs to produce 8,400 units.
Direct materials (128,600 lbs. @ $2.80 per lb.)
$
360,080
Direct labor (37,900 hrs. @ $14.20 per hr.).
538,180
AH = Actual Hours SH = Standard Hours AR = Actual Rate SR = Standard Rate AQ = Actual Quantity SQ = Standard Quantity AP = Actual Price SP = Standard Price (1) Compute the direct materials price and quantity variances. (Indicate the effect of each variance by selecting for favorable, unfavorable, and no variance.)(2) Compute the direct labor rate variance and the direct labor efficiency variance. (Indicate the effect of each variance by selecting for favorable, unfavorable, and no variance.)
Please help with both requirements Thank You
(1) Compute the direct materials price and quantity variances. (Indicate the effect of each variance by selecting for favorable, unfavorable, and no variance.) (2) Compute the direct labor rate variance and the direct labor efficiency variance. (Indicate the effect of each variance by selecting for favorable, unfavorable, and no variance.) Complete this question by entering your answers in the tabs below. Required 1 Required 2 Compute the direct materials price and quantity variances. Indicate whether each variance is favorable or unfavorable. Actual Cost Standard Cost SQ = Standard Quantity AP = Actual Price SP = Standard Price (1) Compute the direct materials price and quantity variances. (Indicate the effect of each variance by selecting for favorable, unfavorable, and no variance.) (2) Compute the direct labor rate variance and the direct labor efficiency variance. (Indicate the effect of each variance by selecting for favorable, unfavorable, and no variance.) Complete this question by entering your answers in the tabs below. Required 1 Required 2 Compute the direct labor rate variance and the direct labor efficiency variance. Indicate whether each variance is favorable or unfavorable. Actual Cost Standard Cost
Answer & Explanation
Solved by verified expert
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
Unlimited Question Access with detailed Answers
Zin AI - 3 Million Words
10 Dall-E 3 Images
20 Plot Generations
Conversation with Dialogue Memory
No Ads, Ever!
Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!