Reducir Inc., produces two different types of hydraulic cylinders. Reducir produces a major subassembly for...

50.1K

Verified Solution

Question

Accounting

  1. Reducir Inc., produces two different types of hydraulic cylinders. Reducir produces a major subassembly for the cylinders in the cutting and welding department. Other parts and the subassembly are then assembled in the assembly department. The activities, expected costs, and drivers associated with these two manufacturing processes are as follows:

Process

Activity

Cost

Activity Driver

Expected Quantity

Cutting and welding

Welding

$2,000,000

Welding hours

4,000

Machining

$1,00,000

Machine hours

10,000

Inspecting

$50,000

No. of inspections

1,000

Materials handling

$72,000

No. Of moves

12,000

Setups

$400,000

No. of setups

100

Total

$3,522,000

Assembly

Changeover

$28,000

Changeover hours

1,000

Rework

$50,000

Rework orders

50

Testing

$40,000

No. of tests

750

Material handling

$60,000

No. of parts

50,000

Engineering support

$70,000

Engineering hours

2,000

Total Cost

$248,000

  1. Other overhead activities, their costs, and drivers are as follows:

Activity

Cost

Activity Driver

Expected Quantity

Purchasing

$50,000

Purchase requisitions

500

Receiving

$70,000

Receiving orders

2,000

Paying suppliers

$80,000

No. of invoices

1,000

Providing space and utilities

$30,000

Machine hours

10,000

Total Cost

$230,000

  1. Other production information concerning the two hydraulic cylinders is also provided as follows:

Cylinder A

Cylinder B

Units produced

1,500

3,000

Welding hours

1,600

2,400

Machine hours

3,000

7,000

Inspections

500

500

Moves

7,200

4,800

Setups

45

55

Changeover hours

540

460

Rework orders

5

45

Tests

500

250

Parts

40,000

10,000

Engineering hours

1,500

500

Requisitions

425

75

Receiving orders

1,800

200

Invoices

650

350

  1. Using a plantwide rate based on machine hours, calculate the total overhead cost assigned to each product and the unit overhead cost.
  2. Using activity rates, calculate the total overhead cost assigned to each product and the unit overhead cost. Comment on the accuracy of the plantwide rate.
  3. Determine the percentage of total costs represented by the three most expensive activities.
  4. Allocate all other activities to the three activities identified in part a. Allocate all the other activity costs to the three activities in proportion to their individual activity costs. Now assign these total costs to the products using the drivers of the three chosen activities.
  5. Using the costs assigned in part a, calculate the percentage error using the ABC costs as a benchmark. Comment on the value and advantage of this ABC simplification

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students