Read the assignment description carefully and please submit your homework in PDF format only and...

60.1K

Verified Solution

Question

Finance

Read the assignment description carefully and please submit your homework in PDF format only and bind the assignment into one document. Also, please name the file starting with your last name.

image

image

image

image

image

image

image

image

You are the Construction Manager on $20,000,000 Hospital Addition. You will be asked to prepare a combined change order complete with the following documents: 1. A letter to the Owner which will be the instructor of the Course describing the change order in accordance with the Lecture notes. Your letter should include the reason for the change order, the scope of the change order and if the change order is value added or the result of unforeseen conditions. 2. The Form of the Change Order 3. Time and Material Spreadsheet Part 1 The Owner of the Project has requested that additional sidewalks, storm drainage, traffic striping, paving, and landscaping be performed to an older parking lot that needs some improvements. The Owner has directed the Construction Manager to perform the work as Change Oder to the Original Contract. The General Contractor (GC) has to subcontract the paving, traffic striping and landscaping to other subcontractors. As the Construction Manger you prepared the scope of work for this additional work. The CM and GC negotiated the following raw unit prices including labor, materials, and equipment (profit and overhead have not been applied, but the Contractor is eligible for profit and overhead as specified on page 3) to perform the work. Description 15" Reinforced Pipe Quantity 310 Unit Liner Foot Unit Price $85 Storm Inlets 6 Each $2,750 Performed By General Contractor General Contractor General Contractor Subcontractor Subcontractor Subcontractor Concrete Sidewalks 200 Square Yards $60 Paving Traffic Stripping Landscaping 16,000 1 Square Feet Lump Sum Lump Sum $3.50 $5,000 $25,000 1 Calculate the total cost of the change order based upon the negotiated unit prices and apply the overhead and profit factors described later in this document. 1 Part 2 While the Contractor was excavating to install the storm, drainage related to the parking lot paving, they encountered soil that has a gasoline odor and appears to have an oily sheen. At this point work is stopped and the Contractor must send his crew home due to safety concerns. After reviewing some records and consulting with the Owner it is discovered that an abandoned gasoline storage tank is buried beneath the older parking lot. Current State regulations require that the underground fuel storage tank must be removed and disposed of. Furthermore, all the contaminated soil must be excavated and disposed at a licensed disposal facility. All of the excavated material has to be replaced with Dense Graded Aggregate at a material cost of $25 per cubic yard including delivery. This work must be performed immediately on a time and material basis (T&M). The scope of work of the T&M work will include the following: 1. The Contractor must be compensated for the delay in the work because he had to pay his crew for two days while the research into the cause of the contaminated soil was determined. The crew consisted of the following: a. Two Class B Equipment Operators b. One Labourer Foreman C. Three Labourers 2. The Contractor hired an environmental consultant to perform soil sampling. A total of 25 samples were taken at cost of $400 per sample. 3. The Contractor also has to purchase 30 rolls of plastic sheeting at $10 per roll to cover the stockpiled soil. He also has to purchase 125 hay bales for soil erosion at $5.00 per bale and 300 linear feet of silt fence at $2.00 per foot. 4. The area of contaminated soil measures 40-feet by 50-feet by 15-feet deep. The disposal facility charges a tipping fee of $125 per ton to dispose of the contaminated soil. A cubic yard of soil is 1.5 tons per cubic yard. Additionally, the Contractor has to rent dump trucks at a monthly rental cost of $15,000 and operating cost of $12 per hour to transport the soil to the disposal facility. Each truck holds 25 tons and can make to two trips per day. The Contractor hires two trucks per day and the trucks drivers are paid a wage of $35.25 per hour with fringe benefits of $17.10 per hour. 5. The Contractor hired a subcontractor to remove the underground storage tank at a lump sum of $15,000. 6. The General Contractor used the following crew to excavate the contaminated soil and place the clean fill. 2 a. b. Three Class B Equipment Operators One Labourer Foreman Four Labourers C. The Laborers and Foreman worked for a total of 80 hours (400 Total man hours) this was agreed upon by the CM and the Contractor's Superintendent. The Equipment Operators man-hours will be based upon the hours that the heavy equipment was operated. The following company owned heavy equipment was utilized: 1. Kobelco SK295LC Track Mounted Excavator - 80Hrs 2. Deere 724K Front End Loader - 80Hrs 3. Roller Compactor - 56 Hrs (Monthly Rental $12,000 and Operating cost $12.50 per hour) You will need to calculate the volume of contaminated soil, clean fill, cost of subcontractors, equipment rental, tipping fees (considered a subcontractor), materials and labor associated with this change order. By Contract the Contractor is permitted to charge 10% overhead and 15% profit on all Materials and Labor of his own forces. 10% profit on all equipment and all subcontractors, no overhead can be applied. You can use the labor rates listed in the spreadsheet presented in Lecture 5 with a labor burden of 1.32, the equipment rates can be found in the attached copies of the Blue Book unless described herein. Operating costs can be charged and use the 176 factor to determine the hourly rental rates. This additional work is to be applied to an original $20,000,000 contract that has already had two change orders in the amount of $605,500. It is important in your summary to advise the Owner if this additional change order will approach the 20% threshold. Also, the Contract has a 360-day duration and the Contractor has requested a 90-day extension to the Contract for this additional work, be sure to document this request in the change order documents. It is best to calculate the cost of each part of the change order separately and combine the totals into one change order. 3 EXCAVATING 9-18 9.28 Estimated Operating Hourly $ Cost $/Hr. 39.00 40.00 20.65 21.25 1,765.00 98 hp 172 hp 540.00 400.00 66.00 61.00 81.00 60.00 61.00 63.00 77.00 85.00 90.00 . 41.35 33.90 50.40 34.75 37.50 47.15 49.90 56.30 61.80 71.85 76.10 86.80 19.70 22.50 21.50 105.00 305 hp 1,080.00 105.00 135.00 41.00 44.00 46.00 8 mt 53 hp 80 26.7 mt 2545.00 PC200LC-8 PC220LC-8 PC300LC-8 (2010) 32.7 mt 445.00 CRAWLER MOUNTED HYDRAULIC EXCAVATORS (cont.) (General Purpose bucket included in rate, unless otherwise noted.) Estima Operating $ Cost St Operating Model (Yr.Disc.) Bucket Capacity Weight HP Monthly $ Weekly $ Daily $ DIESEL POWERED (CONT.) IHI 0 65NX (2010) .2616 cu yd 6.5318 mt 80.30 55 hp 3,735.00 1,045.00 260.00 BOVX .33 cu yd 8.2 mt 58.7 hp 3,785.00 10475 1,060.00 265.00 152 65 JCB 171.40 D 38.70 JS200 NA 20.7 mt 6,310.00 128 hp 0 JZ140 (2012) 440.00 52.75 1.2 cu yd 13.7 mt 5,810.00 1,625.00 405.00 56.25 JZ235 N/A N/A JS145 7,680.00 2,150.00 .57 cu yd 14.6 mt 98 hp 5,715.00 JS160 1,600.00 .84 cu yd 17.1 mt 123 hp JS190LC (2012) 5,810.00 1,625.00 405.00 1.18 cu yd 19.6 mt 166 3 21 65 hp 5,980.00 1,675.00 JS220 420.00 1.18 cu yd 20.3 mt 172 hp 9 7,355.00 2,060.00 515.00 3875 JS260 (2012) 1.58 cu yd 23.7 mt 197 hp 8,065.00 2,260.00 5225 565.00 JS290 (2012) 1.81 cu vd 31.04 mt 216 hp 8,565.00 2,400.00 600.00 JS330 2.37 cu vd een 33 mt 271 hp 9,765.00 2,735.00 685.00 JS360LC (2010) cu vd cu ya 37.57 mt 271 hp 10,170.00 2,850.00 715.00 20.85 JS460 2.68 cu yd 46.8 mt 12,710.00 3,560.00 890.00 2130 8065 .13 cu yd 6.6 mt 51.1 hp 3,850.00 270.00 2800 8080 ZTS (2010) .19 cu yd 8.3 mt 57.7 hp 4,185.00 1,170.00 295.00 8085 .19 cu yd 4,345.00 1,215.00 305.00 KOBELCO 42.60 SK115DZ LC MARK IV 4725 .5 cu yd 12.9 mt 86 hp 4,385.00 1,230.00 310.00 51.70 70SR .29 cu yd 7.8 mt 56 hp 4,880.00 1,365.00 340.00 .46 cu yd 8.6 mt 56 hp 4,675.00 1,310.00 330.00 140SR .44 cu yd 14.7 mt 6,890.00 1,930.00 485.00 ED150 So 16.2 mt 7,610.00 2,130.00 535.00 217 30 NA 20 153 hp 8,775.00 2,455.00 615.00 2025 235SRLC 153 hp 10,045.00 2,815.00 705.00 22.20 SK 170LC 125 hp 7.615.00 2,130.00 535.00 SK210LC ACERA MARK 8 1.14 cu yd 21.7 mt 9,090.00 635.00 SK260LC (2011) 1.3 cu yd 25.99 mt 181 hp 8,945.00 2,505.00 625.00 34 50 SK295LC (2011) 1.59 cu yd 30.3 mt 194 hp 10,500.00 2,940.00 735.00 40.60 SK350LC ACERA MARK 8 (2011) 1.86 cu yd 36.1 mt 264 hp 12,575.00 3,520.00 880.00 49.95 52.75 KOMATSU 57.60 61.15 PC78US-6 (2010) 37 cu yd 7.2 mt 54 hp 4,570.00 1,280.00 PC88MR-8 80.30 .37 cu yd 8.4 mt 65 hp 4,565.00 1,280.00 320.00 104.75 PC130-8 .65 cu yd 12.6 mt 92 hp 6,435.00 1,800.00 450.00 152.90 PC138USLC-8 cu yd 14.3 mt 92 hp 7,050.00 1,975.00 495.00 176.95 PC160LC-7 (2010) cu yd 16.6 mt 115 hp 6,645.00 1,860.00 465.00 PC160LC-8 .85 cu yd 16.9 mt 115 hp 7,030.00 1,970.00 495.00 PC200-8 cu yd 20.1 mt 148 hp 7,625.00 2,135.00 535.00 wedd cu yd 21.4 mt 148 hp 7,330.00 2,050.00 515.00 57.60 24.9 mt 168 hp 9,410.00 2,635.00 660.00 140 h 82.35 PC228USLC-3 (2010) 22.9 mt 148 hp 8,950.00 2,505.00 625.00 22.70 PC270LC-8 30.1 mt 60. 187 hp 9,965.00 2,790.00 700.00 26.65 0.60 39.4 mt PC300HD-8 (2010) 246 hp 12,855.00 3,600.00 900.00 46.50 335.4 mt 246 hp 12,295.00 3,445.00 860.00 33.70 PC308USLC-3 187 hp 11,215.00 3,140.00 785.00 36.15 PC350LC-8 35.4 mt 35.4 mt 246 hp 10,820.00 3,030.00 760.00 45.35 PC360LC-10 35.8 mt 257 hp 13,515.00 3,785.00 60.30 PC400LC-8 (2010) 45.7 mt 45.7 mt 16,170.00 4,530.00 1,135.00 73.85 PC450LC-8 44.8 mt 345 hp 13,895.00 3,890.00 975.00 94.65 PC490LC-10 48.5 mt 19,045.00 5,335.00 1,335.00 105.00 PC600LC-8 3.53 cu yd 60 mt 429 hp 23,695.00 6,635.00 1,660.00 155.20 PCBOOLC-8 487 hp 31,265.00 8,755.00 2,190.00 PC1250-8 6.5 cu yd 672 hp 35,970.00 10,070.00 2,520.00 PC1250LC-8 6.5 cu yd 113.5 mt 672 hp 34,355.00 9,620.00 2,405.00 94 hp 94 hp 215SRLC .5 cu yd 1.13 cu yd 24.8 m 47.00 51.00 50.00 73.00 80.00 . 92.00 105.00 80.00 95.00 94.00 110.00 130.00 27.55 22.15 22.45 34.60 9.00 36.20 50.65 voor 53.05 40.25 49.00 57.55 63.05 79.70 .95 cu yd 17.15 mt 150 hp 320.00 48.00 48.00 68.00 74.00 1960 70.00 4.00 74.00 149.00 80.00 77.00 99.00 94.00 105.00 135.00 130.00 120.00 115.00 140.00 170.00 * 145.00 2010 200.00 250.00 330.00 380.00 360.00 22.05 23.45 31.75 34.90 54.34 38.65 38.45 10.10 46.40 46.25 54.75 50.90 58.70 77.40 76.20 61.90 70.60 20 78.20 102.55 94.70 108.20 134.25 166.65 214.30 208.15 345 hp 359 hp 4.05 cu yd 81.6 mt 106.5 mt nd Half 2015 2nd Half 2015 Copyright 2015 by EquipmentWatch. All rights reserved. Rental Rate Blue Book, Volume 1 1-800-669-3282 $10-21 TRACTORS & EARTHMOVING Estimated Operating Cost $/HC Daily $ Hourly $ Model (Yr.Disc DIESEL POW 2,840.00 SKID STEER LOADERS (cont.) (Includes bucket and ROPS, unless otherwise noted.) Model (Yr.Disc.) Operating Capacity HP Monthly $ Weekly $ DIESEL POWERED BOBCAT 543 800 lbs 21.5 hp 1,310.00 365.00 543 21.5 hp 1,325.00 370.00 A(with EROPS) 743 1300 lbs 36 hp 1,730.00 3000 lbs 81 hp 3,365.00 940.00 $70 700 lbs 23.5 hp 1,710.00 480.00 S100 1000 lbs 2,190.00 615.00 $130 1300 lbs 49 hp son 2,430.00 680.00 S150 Sed 1500 lbs 49 hp 2,365.00 660.00 S160 1600 lbs CA 61 hp 700 2.505.00 700.00 S175 1750 lbs he 49 hp 2.245.00 630.00 S185 1850 lbs 61 hp 2545.00 715.00 S205 2050 lbs 66 hp S220 (2010) 2,000.00 805.00 2200 lbs 75 hp 760.00 S250 2500 lbs 75 hp 795.00 795.00 S300 (2011) 3000 lbs 81 hp 3,310.00 925.00 S330 (2011) 3300 Ibs 85 hp 935.00 S630 74.3 hp 2,860.00 800.00 S650 2690 lbs 74.3 hp 3,295.00 925.00 S750 3200 lbs 85 hp 3,475.00 975.00 CASE DEERE (CON 800 lbs 91.00 93.00 14.00 14.00 7.60 7.60 A300 (2010) 485.00 11.05 21.50 317 2010 $20 (2010) 325 (2010) 228 2010) 332 (2010) GEHL 33.5 hp 8.60 120.00 235.00 120.00 155.00 170.00 165.00 175.00 160.00 180.00 200.00 0.0 190.00 200.00 90 230.00 235.00 200.00 230.00 245.00 18.00 35.00 18.00 23.00 0.00 26.00 25.00 26.00 24 24.00 27 27.00 30.00 29.00 40.00 30.00 35.00 35.00 30.00 35.00 37.00 11.55 14.30 14.15 16.10 10.10 13.80 16.25 26 17.60 1.ou 2,880.00 2,710.00 SL5625 3640E (2010) 240E (2012 SLDE TURBO 310E 19.15 HYUNDA 3,345.00 2180 lbs 18.80 21.30 21.90 18.60 19.60 21.40 2300 lbs 2300 lbs 72 hp 72 hp 2.715.00 2,855.00 760.00 800.00 190.00 200.00 29.00 30.00 18.55 18.90 50 SERIES SERIES 90 SERES SERIES New Gene New Gener 30 New Gener 20 New Gener - SERIES 2200 lbs 2200 lbs 82 hp 82 hp 2,650.00 2.780.00 740.00 780.00 185.00 195.00 28.00 29.00 435 (2010) 435 (2010) A(with EROPS) 440 440 A(with EROPS) 465 (2010) 465 (2010) A(with EROPS) 1825 1835 1845 465 SERIES 3 (2010) 19.45 19.75 3000 lbs 3000 lbs 82 hp 82 hp 3,435.00 3,570.00 960.00 1,000.00 240.00 250.00 36.00 38.00 21.65 22.00 OMATSU 800 lbs 1200 lbs 1700 lbs 3000 lbs 2500 lbs 25 hp 34 hp 45 hp 83 hp 1,545.00 2,050.00 1,920.00 3,325.00 3,155.00 435.00 575.00 540.00 930.00 885.00 110.00 145.00 135.00 235.00 220.00 17.00 22.00 20.00 35.00 33.00 8.55 11.45 12.65 21.70 20.66 SR250 15-5 2010 21820-5 2010 04020-5 2016 20-5 2010 225-5 2010 USTANG 84 hp CATERPILLAR 165.00 216B SERIES 2 (2010) 216B SERIES 3 226B SERIES 2 (2010) 226B SERIES 3 232B SERIES 2 (2010) 236B SERIES 2 (2010) 236B SERIES 3 1400 lbs 1400 lbs 1500 lbs 1500 lbs 14.45 14.40 15.95 1900 lbs 15.80 16.05 242B SERIES 2 (2010) 49 hp 47 hp 57 hp 56 hp 57 hp 70 hp 71 hp 57 hp 56 hp 73 hp 70 hp 71 hp 1950 lbs 1950 lbs 2100 lbs w 2150 lbs 2150 lbs 2500 lbs 40005 2650 lbs 2350 lbs 2700 lbs 3250 lbs 2,320.00 2,570.00 2,440.00 2,615.00 2,575.00 2,640.00 2,885.00 2,675.00 2010 2,910.00 2,855.00 2,985.00 3,130.00 3,280.00 3,535.00 242B SERIES 3 246C 252B SERIES 2 (2010) 252B SERIES 3 256C 650.00 720.00 685.00 730.00 0. 720.00 740.00 810.00 2100 7 750.00 od 815.00 . 800.00 be on 835.00 875.00 920.00 990.00 895.00 180.00 170.00 185.00 180.00 185.00 20500 205.00 100 190.00 205.00 200.00 210.00 220.00 230.00 250.00 225.00 25.00 27.00 26.00 28.00 27.00 28.00 31.00 29.00 31.00 30.00 32.00 33.00 35.00 38.00 34.00 18.11 18.10 18.25 16.25 10. 16.2 18.35 18.05 18.70 20.60 21.25 21.45 82 hp HOLLAN 2620 272C 82 hp 90 hp 3,190.00 2010 DEERE 313 315 1260 lbs 1500 lbs 45 hp 45 hp 2,260.00 2,335.00 635.00 655.00 $0.00 165.00 24.00 25.00 13.35 13.55 $9-18 Copyright 2015 by EquipmentWatch. All rights reserved. Rental Rate Blue Book, Volume 1 1-800-669-3282 2nd Half 205 Change Order No. te of Issuance: ner: North Hudson Sewerage Authority contractor: Engineer: Project: Effective Date: Owner's Contract No.: Contractor's Project No.: Engineer's Project No.: Contract Name: The Contract is modified as follows upon execution of this Change Order: Description: Attachments: [List documents supporting change) CHANGE IN CONTRACT PRICE CHANGE IN CONTRACT TIMES (note changes in Milestones if applicable) Original Contract Price: Original Contract Times: Substantial Completion: $ Ready for Final Payment: days or dates [Increase] (Decrease] from previously approved Change [Increase] [Decrease] from previously approved Change Orders No. to No.__ Orders No. to No .: Substantial Completion: $ Ready for Final Payment: days Contract Price prior to this Change Order: Contract Times prior to this Change Order: Substantial Completion: $ Ready for Final Payment: days or dates [Increase) [Decrease] of this Change Order: [Increase] (Decrease] of this Change Order: Substantial Completion: $ Ready for Final Payment: days or dates Contract Price incorporating this Change Order: Contract Times with all approved Change Orders: Substantial Completion: $ Ready for Final Payment: days or dates RECOMMENDED: ACCEPTED: ACCEPTED: By: By: By: Engineer (if required) Owner (Authorized Signature) Contractor (Authorized Signature) Title Title Date: Date Title: Date Approved by Funding Agency (if applicable) By: Title: Date: Client Name Project Name Water Main Repair Edgewater Avenue/Victoria Terrace June 9, 2010 Item Description Unit No. Labd Quantity OT Hours OT Hours Con Final Quantities Unit Price Labor Burden Burdened Labor Fringe Benefits Total Rate Amount Material 1 2 3 Water Main Pipe Dense Graded Aggregate Bituminous Pavement LF Ton Ton 125 20 10 $ $ $ 75.00 15.00 75.00 $ 9,375.00 $ 300.00 $ 750.00 Subtotal $ 10,425.00 HR 1 1 1 24 4 32 4 2 12 2,160.81 413.28 2,790.60 1 2 3 4 5 6 7 8 9 10 Labor Operating Engineer (Crane) Operating Engineer (Class B) Labor - Foreman Labor - Steward Labor - Mason Laborer Dock Builder . Foreman Dock Builder Carpenter 1 HR HR HR HR HR HR HR HR 0 6 3 18 0 18 0 0 0 0$ 30$ 7 $ 50 $ 0 $ 42 $ 0 $ 0 $ 0 $ 42.27 39.01 30.85 28.40 28.00 28.00 42.55 37.00 40.12 1.306 $ 1.306 $ 1.306 $ 1.305 $ 1.305 $ 3 1.305 $ 1.3051 $ 1.3053 1.305 $ 55.203 50.95$ 40.29 $ 37.06 $ 36.54 $ 36.54 $ 55.53 $ 48.29 $ 52.36 $ 21.08$ 21.08$ 18.75$ 18.75$ 18.75$ 18.75$ 33.47 $ 33.47 $ 33.47 $ 76.28 $ 72.03 $ 59.04 $ 55.81 $ 55.29 $ 55.29 $ 89.00 $ 81.763 85.83 $ 1 24 12 2,322.18 1 1 1 129 Subtotal $ 7,686.87 L&M Subtotal $ 18,111.87 10% Overhead Subtotal 10% Profit $ 1.811.19 $ 19,923.06 $ 1,992.31 Subtotal $ 21,915.37 28 8 1,274.86 501.86 10 14 15 16 17 24 Company Owned Equipment Rubber Tire Backhoe - Cat 430 Loader - Cat 938 Loader - Cat 966 80 Ton AT Crane - Krupp 60 Ton RT Crane - Grove RT700E Vibro Hammer HR HR HR HR HR HR 1 1 1 1 1 1 Monthly Rental 28 $ 3,455.00 $ 8 $ 3,825.00 $ 01$ 7,590.00 $ 36 $ 17.445.00 $ 0 $ 15,665.00 $ 0 $ 8,755.00 $ MR/176 Operating costs 19.63 $ 25.90 21.73 $ 41.00 43.133 51.00 99.12 $ 102.20 89,01$ 108.35 49.74 $ 49.05 Total Rate $ 45.53 $ $ 62.73 $ $ 94.13 $ $ 201.32 $ $ 197.36 $ $ 98.79 $ Subtotal $ 36 7,247.50 72 9,024.22 No. Labor Quantity Labor Burden Burdened Labor Fringe Benefits Subcontractors Wamer Surveying On-Site Trucking Trucking Disposal of Material 4 Submersible Generator 11 12 13 14 15 Unit LS HR HR HR 33.5 Final Quantities Unit Price $ 1,084.70 $ 90.00 $ 74.85 0 22 Total Rate Amount $ $ $ 3.015.00 $ 1.646.65 $ 6.43 $ Subtotal $ 4,661.65 10% Profit 1$ 466.16 Subtotal $ 5,127.81 $ $ 6.43 16 Total $ 36,067.39 You are the Construction Manager on $20,000,000 Hospital Addition. You will be asked to prepare a combined change order complete with the following documents: 1. A letter to the Owner which will be the instructor of the Course describing the change order in accordance with the Lecture notes. Your letter should include the reason for the change order, the scope of the change order and if the change order is value added or the result of unforeseen conditions. 2. The Form of the Change Order 3. Time and Material Spreadsheet Part 1 The Owner of the Project has requested that additional sidewalks, storm drainage, traffic striping, paving, and landscaping be performed to an older parking lot that needs some improvements. The Owner has directed the Construction Manager to perform the work as Change Oder to the Original Contract. The General Contractor (GC) has to subcontract the paving, traffic striping and landscaping to other subcontractors. As the Construction Manger you prepared the scope of work for this additional work. The CM and GC negotiated the following raw unit prices including labor, materials, and equipment (profit and overhead have not been applied, but the Contractor is eligible for profit and overhead as specified on page 3) to perform the work. Description 15" Reinforced Pipe Quantity 310 Unit Liner Foot Unit Price $85 Storm Inlets 6 Each $2,750 Performed By General Contractor General Contractor General Contractor Subcontractor Subcontractor Subcontractor Concrete Sidewalks 200 Square Yards $60 Paving Traffic Stripping Landscaping 16,000 1 Square Feet Lump Sum Lump Sum $3.50 $5,000 $25,000 1 Calculate the total cost of the change order based upon the negotiated unit prices and apply the overhead and profit factors described later in this document. 1 Part 2 While the Contractor was excavating to install the storm, drainage related to the parking lot paving, they encountered soil that has a gasoline odor and appears to have an oily sheen. At this point work is stopped and the Contractor must send his crew home due to safety concerns. After reviewing some records and consulting with the Owner it is discovered that an abandoned gasoline storage tank is buried beneath the older parking lot. Current State regulations require that the underground fuel storage tank must be removed and disposed of. Furthermore, all the contaminated soil must be excavated and disposed at a licensed disposal facility. All of the excavated material has to be replaced with Dense Graded Aggregate at a material cost of $25 per cubic yard including delivery. This work must be performed immediately on a time and material basis (T&M). The scope of work of the T&M work will include the following: 1. The Contractor must be compensated for the delay in the work because he had to pay his crew for two days while the research into the cause of the contaminated soil was determined. The crew consisted of the following: a. Two Class B Equipment Operators b. One Labourer Foreman C. Three Labourers 2. The Contractor hired an environmental consultant to perform soil sampling. A total of 25 samples were taken at cost of $400 per sample. 3. The Contractor also has to purchase 30 rolls of plastic sheeting at $10 per roll to cover the stockpiled soil. He also has to purchase 125 hay bales for soil erosion at $5.00 per bale and 300 linear feet of silt fence at $2.00 per foot. 4. The area of contaminated soil measures 40-feet by 50-feet by 15-feet deep. The disposal facility charges a tipping fee of $125 per ton to dispose of the contaminated soil. A cubic yard of soil is 1.5 tons per cubic yard. Additionally, the Contractor has to rent dump trucks at a monthly rental cost of $15,000 and operating cost of $12 per hour to transport the soil to the disposal facility. Each truck holds 25 tons and can make to two trips per day. The Contractor hires two trucks per day and the trucks drivers are paid a wage of $35.25 per hour with fringe benefits of $17.10 per hour. 5. The Contractor hired a subcontractor to remove the underground storage tank at a lump sum of $15,000. 6. The General Contractor used the following crew to excavate the contaminated soil and place the clean fill. 2 a. b. Three Class B Equipment Operators One Labourer Foreman Four Labourers C. The Laborers and Foreman worked for a total of 80 hours (400 Total man hours) this was agreed upon by the CM and the Contractor's Superintendent. The Equipment Operators man-hours will be based upon the hours that the heavy equipment was operated. The following company owned heavy equipment was utilized: 1. Kobelco SK295LC Track Mounted Excavator - 80Hrs 2. Deere 724K Front End Loader - 80Hrs 3. Roller Compactor - 56 Hrs (Monthly Rental $12,000 and Operating cost $12.50 per hour) You will need to calculate the volume of contaminated soil, clean fill, cost of subcontractors, equipment rental, tipping fees (considered a subcontractor), materials and labor associated with this change order. By Contract the Contractor is permitted to charge 10% overhead and 15% profit on all Materials and Labor of his own forces. 10% profit on all equipment and all subcontractors, no overhead can be applied. You can use the labor rates listed in the spreadsheet presented in Lecture 5 with a labor burden of 1.32, the equipment rates can be found in the attached copies of the Blue Book unless described herein. Operating costs can be charged and use the 176 factor to determine the hourly rental rates. This additional work is to be applied to an original $20,000,000 contract that has already had two change orders in the amount of $605,500. It is important in your summary to advise the Owner if this additional change order will approach the 20% threshold. Also, the Contract has a 360-day duration and the Contractor has requested a 90-day extension to the Contract for this additional work, be sure to document this request in the change order documents. It is best to calculate the cost of each part of the change order separately and combine the totals into one change order. 3 EXCAVATING 9-18 9.28 Estimated Operating Hourly $ Cost $/Hr. 39.00 40.00 20.65 21.25 1,765.00 98 hp 172 hp 540.00 400.00 66.00 61.00 81.00 60.00 61.00 63.00 77.00 85.00 90.00 . 41.35 33.90 50.40 34.75 37.50 47.15 49.90 56.30 61.80 71.85 76.10 86.80 19.70 22.50 21.50 105.00 305 hp 1,080.00 105.00 135.00 41.00 44.00 46.00 8 mt 53 hp 80 26.7 mt 2545.00 PC200LC-8 PC220LC-8 PC300LC-8 (2010) 32.7 mt 445.00 CRAWLER MOUNTED HYDRAULIC EXCAVATORS (cont.) (General Purpose bucket included in rate, unless otherwise noted.) Estima Operating $ Cost St Operating Model (Yr.Disc.) Bucket Capacity Weight HP Monthly $ Weekly $ Daily $ DIESEL POWERED (CONT.) IHI 0 65NX (2010) .2616 cu yd 6.5318 mt 80.30 55 hp 3,735.00 1,045.00 260.00 BOVX .33 cu yd 8.2 mt 58.7 hp 3,785.00 10475 1,060.00 265.00 152 65 JCB 171.40 D 38.70 JS200 NA 20.7 mt 6,310.00 128 hp 0 JZ140 (2012) 440.00 52.75 1.2 cu yd 13.7 mt 5,810.00 1,625.00 405.00 56.25 JZ235 N/A N/A JS145 7,680.00 2,150.00 .57 cu yd 14.6 mt 98 hp 5,715.00 JS160 1,600.00 .84 cu yd 17.1 mt 123 hp JS190LC (2012) 5,810.00 1,625.00 405.00 1.18 cu yd 19.6 mt 166 3 21 65 hp 5,980.00 1,675.00 JS220 420.00 1.18 cu yd 20.3 mt 172 hp 9 7,355.00 2,060.00 515.00 3875 JS260 (2012) 1.58 cu yd 23.7 mt 197 hp 8,065.00 2,260.00 5225 565.00 JS290 (2012) 1.81 cu vd 31.04 mt 216 hp 8,565.00 2,400.00 600.00 JS330 2.37 cu vd een 33 mt 271 hp 9,765.00 2,735.00 685.00 JS360LC (2010) cu vd cu ya 37.57 mt 271 hp 10,170.00 2,850.00 715.00 20.85 JS460 2.68 cu yd 46.8 mt 12,710.00 3,560.00 890.00 2130 8065 .13 cu yd 6.6 mt 51.1 hp 3,850.00 270.00 2800 8080 ZTS (2010) .19 cu yd 8.3 mt 57.7 hp 4,185.00 1,170.00 295.00 8085 .19 cu yd 4,345.00 1,215.00 305.00 KOBELCO 42.60 SK115DZ LC MARK IV 4725 .5 cu yd 12.9 mt 86 hp 4,385.00 1,230.00 310.00 51.70 70SR .29 cu yd 7.8 mt 56 hp 4,880.00 1,365.00 340.00 .46 cu yd 8.6 mt 56 hp 4,675.00 1,310.00 330.00 140SR .44 cu yd 14.7 mt 6,890.00 1,930.00 485.00 ED150 So 16.2 mt 7,610.00 2,130.00 535.00 217 30 NA 20 153 hp 8,775.00 2,455.00 615.00 2025 235SRLC 153 hp 10,045.00 2,815.00 705.00 22.20 SK 170LC 125 hp 7.615.00 2,130.00 535.00 SK210LC ACERA MARK 8 1.14 cu yd 21.7 mt 9,090.00 635.00 SK260LC (2011) 1.3 cu yd 25.99 mt 181 hp 8,945.00 2,505.00 625.00 34 50 SK295LC (2011) 1.59 cu yd 30.3 mt 194 hp 10,500.00 2,940.00 735.00 40.60 SK350LC ACERA MARK 8 (2011) 1.86 cu yd 36.1 mt 264 hp 12,575.00 3,520.00 880.00 49.95 52.75 KOMATSU 57.60 61.15 PC78US-6 (2010) 37 cu yd 7.2 mt 54 hp 4,570.00 1,280.00 PC88MR-8 80.30 .37 cu yd 8.4 mt 65 hp 4,565.00 1,280.00 320.00 104.75 PC130-8 .65 cu yd 12.6 mt 92 hp 6,435.00 1,800.00 450.00 152.90 PC138USLC-8 cu yd 14.3 mt 92 hp 7,050.00 1,975.00 495.00 176.95 PC160LC-7 (2010) cu yd 16.6 mt 115 hp 6,645.00 1,860.00 465.00 PC160LC-8 .85 cu yd 16.9 mt 115 hp 7,030.00 1,970.00 495.00 PC200-8 cu yd 20.1 mt 148 hp 7,625.00 2,135.00 535.00 wedd cu yd 21.4 mt 148 hp 7,330.00 2,050.00 515.00 57.60 24.9 mt 168 hp 9,410.00 2,635.00 660.00 140 h 82.35 PC228USLC-3 (2010) 22.9 mt 148 hp 8,950.00 2,505.00 625.00 22.70 PC270LC-8 30.1 mt 60. 187 hp 9,965.00 2,790.00 700.00 26.65 0.60 39.4 mt PC300HD-8 (2010) 246 hp 12,855.00 3,600.00 900.00 46.50 335.4 mt 246 hp 12,295.00 3,445.00 860.00 33.70 PC308USLC-3 187 hp 11,215.00 3,140.00 785.00 36.15 PC350LC-8 35.4 mt 35.4 mt 246 hp 10,820.00 3,030.00 760.00 45.35 PC360LC-10 35.8 mt 257 hp 13,515.00 3,785.00 60.30 PC400LC-8 (2010) 45.7 mt 45.7 mt 16,170.00 4,530.00 1,135.00 73.85 PC450LC-8 44.8 mt 345 hp 13,895.00 3,890.00 975.00 94.65 PC490LC-10 48.5 mt 19,045.00 5,335.00 1,335.00 105.00 PC600LC-8 3.53 cu yd 60 mt 429 hp 23,695.00 6,635.00 1,660.00 155.20 PCBOOLC-8 487 hp 31,265.00 8,755.00 2,190.00 PC1250-8 6.5 cu yd 672 hp 35,970.00 10,070.00 2,520.00 PC1250LC-8 6.5 cu yd 113.5 mt 672 hp 34,355.00 9,620.00 2,405.00 94 hp 94 hp 215SRLC .5 cu yd 1.13 cu yd 24.8 m 47.00 51.00 50.00 73.00 80.00 . 92.00 105.00 80.00 95.00 94.00 110.00 130.00 27.55 22.15 22.45 34.60 9.00 36.20 50.65 voor 53.05 40.25 49.00 57.55 63.05 79.70 .95 cu yd 17.15 mt 150 hp 320.00 48.00 48.00 68.00 74.00 1960 70.00 4.00 74.00 149.00 80.00 77.00 99.00 94.00 105.00 135.00 130.00 120.00 115.00 140.00 170.00 * 145.00 2010 200.00 250.00 330.00 380.00 360.00 22.05 23.45 31.75 34.90 54.34 38.65 38.45 10.10 46.40 46.25 54.75 50.90 58.70 77.40 76.20 61.90 70.60 20 78.20 102.55 94.70 108.20 134.25 166.65 214.30 208.15 345 hp 359 hp 4.05 cu yd 81.6 mt 106.5 mt nd Half 2015 2nd Half 2015 Copyright 2015 by EquipmentWatch. All rights reserved. Rental Rate Blue Book, Volume 1 1-800-669-3282 $10-21 TRACTORS & EARTHMOVING Estimated Operating Cost $/HC Daily $ Hourly $ Model (Yr.Disc DIESEL POW 2,840.00 SKID STEER LOADERS (cont.) (Includes bucket and ROPS, unless otherwise noted.) Model (Yr.Disc.) Operating Capacity HP Monthly $ Weekly $ DIESEL POWERED BOBCAT 543 800 lbs 21.5 hp 1,310.00 365.00 543 21.5 hp 1,325.00 370.00 A(with EROPS) 743 1300 lbs 36 hp 1,730.00 3000 lbs 81 hp 3,365.00 940.00 $70 700 lbs 23.5 hp 1,710.00 480.00 S100 1000 lbs 2,190.00 615.00 $130 1300 lbs 49 hp son 2,430.00 680.00 S150 Sed 1500 lbs 49 hp 2,365.00 660.00 S160 1600 lbs CA 61 hp 700 2.505.00 700.00 S175 1750 lbs he 49 hp 2.245.00 630.00 S185 1850 lbs 61 hp 2545.00 715.00 S205 2050 lbs 66 hp S220 (2010) 2,000.00 805.00 2200 lbs 75 hp 760.00 S250 2500 lbs 75 hp 795.00 795.00 S300 (2011) 3000 lbs 81 hp 3,310.00 925.00 S330 (2011) 3300 Ibs 85 hp 935.00 S630 74.3 hp 2,860.00 800.00 S650 2690 lbs 74.3 hp 3,295.00 925.00 S750 3200 lbs 85 hp 3,475.00 975.00 CASE DEERE (CON 800 lbs 91.00 93.00 14.00 14.00 7.60 7.60 A300 (2010) 485.00 11.05 21.50 317 2010 $20 (2010) 325 (2010) 228 2010) 332 (2010) GEHL 33.5 hp 8.60 120.00 235.00 120.00 155.00 170.00 165.00 175.00 160.00 180.00 200.00 0.0 190.00 200.00 90 230.00 235.00 200.00 230.00 245.00 18.00 35.00 18.00 23.00 0.00 26.00 25.00 26.00 24 24.00 27 27.00 30.00 29.00 40.00 30.00 35.00 35.00 30.00 35.00 37.00 11.55 14.30 14.15 16.10 10.10 13.80 16.25 26 17.60 1.ou 2,880.00 2,710.00 SL5625 3640E (2010) 240E (2012 SLDE TURBO 310E 19.15 HYUNDA 3,345.00 2180 lbs 18.80 21.30 21.90 18.60 19.60 21.40 2300 lbs 2300 lbs 72 hp 72 hp 2.715.00 2,855.00 760.00 800.00 190.00 200.00 29.00 30.00 18.55 18.90 50 SERIES SERIES 90 SERES SERIES New Gene New Gener 30 New Gener 20 New Gener - SERIES 2200 lbs 2200 lbs 82 hp 82 hp 2,650.00 2.780.00 740.00 780.00 185.00 195.00 28.00 29.00 435 (2010) 435 (2010) A(with EROPS) 440 440 A(with EROPS) 465 (2010) 465 (2010) A(with EROPS) 1825 1835 1845 465 SERIES 3 (2010) 19.45 19.75 3000 lbs 3000 lbs 82 hp 82 hp 3,435.00 3,570.00 960.00 1,000.00 240.00 250.00 36.00 38.00 21.65 22.00 OMATSU 800 lbs 1200 lbs 1700 lbs 3000 lbs 2500 lbs 25 hp 34 hp 45 hp 83 hp 1,545.00 2,050.00 1,920.00 3,325.00 3,155.00 435.00 575.00 540.00 930.00 885.00 110.00 145.00 135.00 235.00 220.00 17.00 22.00 20.00 35.00 33.00 8.55 11.45 12.65 21.70 20.66 SR250 15-5 2010 21820-5 2010 04020-5 2016 20-5 2010 225-5 2010 USTANG 84 hp CATERPILLAR 165.00 216B SERIES 2 (2010) 216B SERIES 3 226B SERIES 2 (2010) 226B SERIES 3 232B SERIES 2 (2010) 236B SERIES 2 (2010) 236B SERIES 3 1400 lbs 1400 lbs 1500 lbs 1500 lbs 14.45 14.40 15.95 1900 lbs 15.80 16.05 242B SERIES 2 (2010) 49 hp 47 hp 57 hp 56 hp 57 hp 70 hp 71 hp 57 hp 56 hp 73 hp 70 hp 71 hp 1950 lbs 1950 lbs 2100 lbs w 2150 lbs 2150 lbs 2500 lbs 40005 2650 lbs 2350 lbs 2700 lbs 3250 lbs 2,320.00 2,570.00 2,440.00 2,615.00 2,575.00 2,640.00 2,885.00 2,675.00 2010 2,910.00 2,855.00 2,985.00 3,130.00 3,280.00 3,535.00 242B SERIES 3 246C 252B SERIES 2 (2010) 252B SERIES 3 256C 650.00 720.00 685.00 730.00 0. 720.00 740.00 810.00 2100 7 750.00 od 815.00 . 800.00 be on 835.00 875.00 920.00 990.00 895.00 180.00 170.00 185.00 180.00 185.00 20500 205.00 100 190.00 205.00 200.00 210.00 220.00 230.00 250.00 225.00 25.00 27.00 26.00 28.00 27.00 28.00 31.00 29.00 31.00 30.00 32.00 33.00 35.00 38.00 34.00 18.11 18.10 18.25 16.25 10. 16.2 18.35 18.05 18.70 20.60 21.25 21.45 82 hp HOLLAN 2620 272C 82 hp 90 hp 3,190.00 2010 DEERE 313 315 1260 lbs 1500 lbs 45 hp 45 hp 2,260.00 2,335.00 635.00 655.00 $0.00 165.00 24.00 25.00 13.35 13.55 $9-18 Copyright 2015 by EquipmentWatch. All rights reserved. Rental Rate Blue Book, Volume 1 1-800-669-3282 2nd Half 205 Change Order No. te of Issuance: ner: North Hudson Sewerage Authority contractor: Engineer: Project: Effective Date: Owner's Contract No.: Contractor's Project No.: Engineer's Project No.: Contract Name: The Contract is modified as follows upon execution of this Change Order: Description: Attachments: [List documents supporting change) CHANGE IN CONTRACT PRICE CHANGE IN CONTRACT TIMES (note changes in Milestones if applicable) Original Contract Price: Original Contract Times: Substantial Completion: $ Ready for Final Payment: days or dates [Increase] (Decrease] from previously approved Change [Increase] [Decrease] from previously approved Change Orders No. to No.__ Orders No. to No .: Substantial Completion: $ Ready for Final Payment: days Contract Price prior to this Change Order: Contract Times prior to this Change Order: Substantial Completion: $ Ready for Final Payment: days or dates [Increase) [Decrease] of this Change Order: [Increase] (Decrease] of this Change Order: Substantial Completion: $ Ready for Final Payment: days or dates Contract Price incorporating this Change Order: Contract Times with all approved Change Orders: Substantial Completion: $ Ready for Final Payment: days or dates RECOMMENDED: ACCEPTED: ACCEPTED: By: By: By: Engineer (if required) Owner (Authorized Signature) Contractor (Authorized Signature) Title Title Date: Date Title: Date Approved by Funding Agency (if applicable) By: Title: Date: Client Name Project Name Water Main Repair Edgewater Avenue/Victoria Terrace June 9, 2010 Item Description Unit No. Labd Quantity OT Hours OT Hours Con Final Quantities Unit Price Labor Burden Burdened Labor Fringe Benefits Total Rate Amount Material 1 2 3 Water Main Pipe Dense Graded Aggregate Bituminous Pavement LF Ton Ton 125 20 10 $ $ $ 75.00 15.00 75.00 $ 9,375.00 $ 300.00 $ 750.00 Subtotal $ 10,425.00 HR 1 1 1 24 4 32 4 2 12 2,160.81 413.28 2,790.60 1 2 3 4 5 6 7 8 9 10 Labor Operating Engineer (Crane) Operating Engineer (Class B) Labor - Foreman Labor - Steward Labor - Mason Laborer Dock Builder . Foreman Dock Builder Carpenter 1 HR HR HR HR HR HR HR HR 0 6 3 18 0 18 0 0 0 0$ 30$ 7 $ 50 $ 0 $ 42 $ 0 $ 0 $ 0 $ 42.27 39.01 30.85 28.40 28.00 28.00 42.55 37.00 40.12 1.306 $ 1.306 $ 1.306 $ 1.305 $ 1.305 $ 3 1.305 $ 1.3051 $ 1.3053 1.305 $ 55.203 50.95$ 40.29 $ 37.06 $ 36.54 $ 36.54 $ 55.53 $ 48.29 $ 52.36 $ 21.08$ 21.08$ 18.75$ 18.75$ 18.75$ 18.75$ 33.47 $ 33.47 $ 33.47 $ 76.28 $ 72.03 $ 59.04 $ 55.81 $ 55.29 $ 55.29 $ 89.00 $ 81.763 85.83 $ 1 24 12 2,322.18 1 1 1 129 Subtotal $ 7,686.87 L&M Subtotal $ 18,111.87 10% Overhead Subtotal 10% Profit $ 1.811.19 $ 19,923.06 $ 1,992.31 Subtotal $ 21,915.37 28 8 1,274.86 501.86 10 14 15 16 17 24 Company Owned Equipment Rubber Tire Backhoe - Cat 430 Loader - Cat 938 Loader - Cat 966 80 Ton AT Crane - Krupp 60 Ton RT Crane - Grove RT700E Vibro Hammer HR HR HR HR HR HR 1 1 1 1 1 1 Monthly Rental 28 $ 3,455.00 $ 8 $ 3,825.00 $ 01$ 7,590.00 $ 36 $ 17.445.00 $ 0 $ 15,665.00 $ 0 $ 8,755.00 $ MR/176 Operating costs 19.63 $ 25.90 21.73 $ 41.00 43.133 51.00 99.12 $ 102.20 89,01$ 108.35 49.74 $ 49.05 Total Rate $ 45.53 $ $ 62.73 $ $ 94.13 $ $ 201.32 $ $ 197.36 $ $ 98.79 $ Subtotal $ 36 7,247.50 72 9,024.22 No. Labor Quantity Labor Burden Burdened Labor Fringe Benefits Subcontractors Wamer Surveying On-Site Trucking Trucking Disposal of Material 4 Submersible Generator 11 12 13 14 15 Unit LS HR HR HR 33.5 Final Quantities Unit Price $ 1,084.70 $ 90.00 $ 74.85 0 22 Total Rate Amount $ $ $ 3.015.00 $ 1.646.65 $ 6.43 $ Subtotal $ 4,661.65 10% Profit 1$ 466.16 Subtotal $ 5,127.81 $ $ 6.43 16 Total $ 36,067.39

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students