Ralph Co manufactures products on a job-order basis. Job 4 is anorder for 100...

50.1K

Verified Solution

Question

Accounting

Ralph Co manufactures products on a job-order basis. Job 4 is anorder for 100 units. It requires $3,000 direct materials, $1,000direct labor, and $1,500 overhead applied based on 150% the directlabor hours. After inspection, 2 units required rework whichrequired $80 additional direct labor costs and $60 ofmaterials.

(1) If the rework is considered normal spoilage due to thenature of the job, determine the cost of Job 4. Prepare the journalentry for overhead.

(2) If the rework is considered normal spoilage, determine thecost of Job 4. Prepare the journal entry for overhead.

(3) If the rework is considered abnormal spoilage, determine thecost of Job 4. Prepare the journal entry for overhead control?

Answer & Explanation Solved by verified expert
4.0 Ratings (488 Votes)
1a cost of Job 4 Particulars Amount Direct Materials300060 3060 Direct Labour100080 1080 Overhead1080150 1620 Total Cost 5760 b Since all the costs are added to the Job order cost no other entry is required    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Transcribed Image Text

In: AccountingRalph Co manufactures products on a job-order basis. Job 4 is anorder for 100 units....Ralph Co manufactures products on a job-order basis. Job 4 is anorder for 100 units. It requires $3,000 direct materials, $1,000direct labor, and $1,500 overhead applied based on 150% the directlabor hours. After inspection, 2 units required rework whichrequired $80 additional direct labor costs and $60 ofmaterials.(1) If the rework is considered normal spoilage due to thenature of the job, determine the cost of Job 4. Prepare the journalentry for overhead.(2) If the rework is considered normal spoilage, determine thecost of Job 4. Prepare the journal entry for overhead.(3) If the rework is considered abnormal spoilage, determine thecost of Job 4. Prepare the journal entry for overhead control?

Other questions asked by students