Questions is about PLC Project. 13.2 Expand on Installation Acceptance Testing, ie: when and what would you...

80.2K

Verified Solution

Question

Electrical Engineering

Questions is about PLC Project.

13.2 Expand on Installation Acceptance Testing, ie: when andwhat would you expect to be doing / checking.

13.3 Expand on Start-Up Testing , ie: when and what would youexpect to be doing / checking.

Answer & Explanation Solved by verified expert
4.1 Ratings (460 Votes)
In programmable logic controller we need to do two types of testing these are as follows 1 Factory acceptance test 2 Installation acceptance test For installation    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students