Question 3: Percentage of Completion Method (12 marks) On January 1, 2017, Eagle Construction Ltd....
60.1K
Verified Solution
Question
Accounting
Question 3:
Percentage of Completion Method (12 marks) On January 1, 2017, Eagle Construction Ltd. started a construction project for $4,500,000. Relevant data for 2017 and 2018 are as follows:
2017 2018
Current year construction costs $3,300,000 $ 620,000
Estimated remaining costs to complete 600,000 -0-
Current year billings 3,100,000 1,400,000
Current year collections 3,000,000 1,500,000
Required: Calculate the following amounts for each method:
Completed Percentage-of Contract Completion 2017 2018 2017 2018
a) Gross Profit $ $ $ $
b) Construction in progress year-end balance $ $ $ $
c) Costs in excess of billings (Billings in excess of costs) $ $ $ $
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
- Unlimited Question Access with detailed Answers
- Zin AI - 3 Million Words
- 10 Dall-E 3 Images
- 20 Plot Generations
- Conversation with Dialogue Memory
- No Ads, Ever!
- Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Other questions asked by students
StudyZin's Question Purchase
1 Answer
$0.99
(Save $1 )
One time Pay
- No Ads
- Answer to 1 Question
- Get free Zin AI - 50 Thousand Words per Month
Unlimited
$4.99*
(Save $5 )
Billed Monthly
- No Ads
- Answers to Unlimited Questions
- Get free Zin AI - 3 Million Words per Month
*First month only
Free
$0
- Get this answer for free!
- Sign up now to unlock the answer instantly
You can see the logs in the Dashboard.