Question 1: Activity Based Costing (25 marks) The Try Corporation has a...
70.2K
Verified Solution
Question
Accounting
Question 1: Activity Based Costing (25 marks)
The Try Corporation has a machining facility specializing in jobs for the aircraft-components market. Try's previous simple job-costing system had two direct-cost categories (direct materials and direct manufacturing labor) and a single indirect-cost pool (manufacturing overhead, allocated using direct manufacturing labor-hours). The indirect cost-allocation rate of the simple system for 2016 would have been $115 per direct manufacturing labor-hour.
Recently a team with members from product design, manufacturing, and accounting used an ABC approach to refine its job-costing system. The two direct-cost categories were retained. The team decided to replace the single indirect-cost pool with five indirect-cost pools. The cost pools represent five activity areas at the plant, each with its own supervisor and budget responsibility. Pertinent data are as follows:
Activity Area
Cost-Allocation Base
Cost-Allocation Rate
Materials handling
Parts
$ 0.40
Lathe work
Lathe turns
0.20
Milling
Machine-hours
20.00
Grinding
Parts
0.80
Testing
Units tested
15.00
Information-gathering technology has advanced to the point at which the data necessary for budgeting in these five activity areas are collected automatically.
Two representative jobs processed under the ABC system at the plant in the most recent period had the following characteristics:
Job 410
Job 411
Direct material cost per job
$ 9,700
$59,900
Direct manufacturing labor cost per job
$750
$11,250
Number of direct manufacturing labor-hours per job
25
375
Parts per job
500
2,000
Lathe turns per job
20,000
59,250
Machine-hours per job
150
1,050
Units per job (all units are tested)
10
200
Required:
1. Compute the manufacturing cost per unit for each job under the previous simple job-costing system.
2. Compute the manufacturing cost per unit for each job under the activity-based costing system.
3. Compare the per-unit cost figures for Jobs 410 and 411 computed in requirements 1 and 2. Why do the simple and the activity-based costing systems differ in the manufacturing cost per unit for each job? Why might these differences be important to Try Corporation?
(3 marks + 6 marks + 16 marks)
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
- Unlimited Question Access with detailed Answers
- Zin AI - 3 Million Words
- 10 Dall-E 3 Images
- 20 Plot Generations
- Conversation with Dialogue Memory
- No Ads, Ever!
- Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Other questions asked by students
StudyZin's Question Purchase
1 Answer
$0.99
(Save $1 )
One time Pay
- No Ads
- Answer to 1 Question
- Get free Zin AI - 50 Thousand Words per Month
Unlimited
$4.99*
(Save $5 )
Billed Monthly
- No Ads
- Answers to Unlimited Questions
- Get free Zin AI - 3 Million Words per Month
*First month only
Free
$0
- Get this answer for free!
- Sign up now to unlock the answer instantly
You can see the logs in the Dashboard.