Question

Accounting

Q.3 Set. (B) A bill of materials with lead time (in weeks), on-hand quantities, lot sizes and scheduled receipts
for product A are shown below
Numbers within () denotes the number of corresponding items required for one parent item.
Construct BOM tree with structure and for a requirement of 60 units, 120 units of A in week 7 and
week 8 respectively prepare a MRP
image

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students