Q2) what are liquidated damages? Why to include a liquidated damages clause in the contract? Are...

70.2K

Verified Solution

Question

Civil Engineering



Q2) what are liquidated damages? Why to include a liquidateddamages clause in the contract? Are they enforceable? How tocalculate the amount of liquidated damage?

Answer & Explanation Solved by verified expert
3.8 Ratings (365 Votes)
Liquidated damages also referred to as liquidated and ascertained damages are damages whose amount the parties designate during the formation of a contract for the injured party to collect as compensation upon a specific breach An exampleLiquidated damages    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Zin AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students