Project Monitoring and Control Process Plan:
You have a Project Budget for building a five-bedroom house inAshburn, VA. Assume that your building project is two months behindand has a $100,000.00 cost overrun. This should not be a surpriseto you because of the monitoring processes. Identify and discusssome of the monitoring processes that could have alerted you of theschedule and cost problems. What are some of the controlling stepsyou would take to bring both the schedule and the cost back ontrack? Be sure to justify your answers. . Your Project Monitoringand Control Process Plan should be at least two pages including asummarization and conclusion page. If necessary, include data fromthe Project Budget and Project Schedule in the table shown below tosupport your schedule and cost problems.
Unit 5Project: |
Activity Description | Start Date | End Date | Days to complete | Est $ |
| | | | |
Architectural Design | 5/1/2018 | 5/15/2018 | 14 | 50,000 |
Procurement of machinery | 5/15/2018 | 5/30/2018 | 15 | 60,000 |
Hiring Labor | 5/31/2018 | 6/10/2018 | 10 | 120,000 |
Work and Environmental Permits | 7/27/2018 | 8/6/2018 | 10 | 25,000 |
Site Security | 8/18/2018 | 4/30/2020 | 731 | 20,000 |
Concrete | 8/18/2018 | 8/31/2018 | 15 | 80,000 |
Lumber Procurement | 9/1/2018 | 9/11/2018 | 10 | 80,000 |
Material Storage | 9/1/2018 | 4/30/2020 | 637 | 10,000 |
Scaffolding Erection | 9/12/2018 | 9/17/2018 | 5 | 25,000 |
Framing | 9/15/2018 | 1/13/2019 | 120 | 130,000 |
Roofing | 1/14/2019 | 2/13/2019 | 30 | 40,000 |
Plumbing | 2/14/2019 | 3/17/2019 | 30 | 30,000 |
Electrical | 3/18/2019 | 4/17/2019 | 30 | 30,000 |
HVAC | 4/18/2019 | 6/2/2019 | 45 | 40,000 |
Windows and Doors | 6/3/2019 | 8/2/2019 | 60 | 20,000 |
Drywall | 8/3/2019 | 9/12/2019 | 40 | 45,000 |
Interior Design | 9/13/2019 | 10/23/2019 | 40 | 15,000 |
Paint and Wood Finishing | 10/24/2019 | 12/23/2019 | 60 | 40,000 |
Cabinetry | 12/24/2019 | 1/8/2020 | 15 | 40,000 |
Plumbing Fixtures | 12/24/2019 | 1/8/2020 | 15 | 20,000 |
Lighting Fixtures | 12/24/2019 | 1/8/2020 | 15 | 20,000 |
Flooring | 1/9/2020 | 1/30/2020 | 21 | 30,000 |
Interior Decorator and Decorations | 1/31/2020 | 2/20/2020 | 20 | 20,000 |
Exterior Rock | 2/21/2020 | 3/22/2020 | 30 | 50,000 |
Landscaping | 3/23/2020 | 4/15/2020 | 23 | 30,000 |
Cost of Construction | | | | 1,040,000 |
Contingency (2%) | 4/16/2020 | 4/30/2020 | 14 | 19,800 |
Total | | | | 1,059,800 |