Project Management Analytics Exercise This is an example of a construction project. The construction for a large...
60.1K
Verified Solution
Question
General Management
Project Management Analytics Exercise
This is an example of a construction project. The constructionfor a large corporate building must be started by February19th and completed by the end of the year. The legalcontract for the project includes a penalty of $10,000 for everyweek of delay beyond December 31st. This implies 315days or 45 weeks for the expected project duration assuming aseven-day work schedule and no holidays in between!
The details of the project activities are as follows –
The project begins with clearing the site, an activity thattakes eight weeks. Once the site is cleared, laying of thesubsurface drainage takes another eight weeks, followed by fillingof the earth which takes 14 weeks. Only after this activity iscompleted can installation of the artificial turf outside of thebuilding can start – the task then takes 12 weeks. Simultaneously,the work on the building can also start once the site iscleared.
The work on the building starts first by excavating and then bypouring of the concrete basement. Each of these activities takes 4weeks to complete. Next comes the construction of the walls (12weeks), followed by constructing the roof (13 weeks). The interiorsare then completed (5 weeks) followed by internal painting (4weeks). However, painting cannot be started until electrical workis completed (4 weeks). The electrical work cannot be started untilthe outside power lines are laid (8 weeks), which needs anadditional activity of getting the permits before it can bestarted. The permit takes 4 weeks. Assume that you would start onthe permits after the excavation activity for the buildingbegins.
Once the roof of the building is erected, work can startsimultaneously on the outside lighting (5 weeks), and on thesignage and other external landscaping (4 weeks). For simplicity,assume you start the project on February 19th and youfollow a 7-day work schedule where each week of an activity’sduration takes 7 days.
Analyze the following questions based on the estimates of theabove activities -
1) When do you complete the project?
Project Management Analytics Exercise
This is an example of a construction project. The constructionfor a large corporate building must be started by February19th and completed by the end of the year. The legalcontract for the project includes a penalty of $10,000 for everyweek of delay beyond December 31st. This implies 315days or 45 weeks for the expected project duration assuming aseven-day work schedule and no holidays in between!
The details of the project activities are as follows –
The project begins with clearing the site, an activity thattakes eight weeks. Once the site is cleared, laying of thesubsurface drainage takes another eight weeks, followed by fillingof the earth which takes 14 weeks. Only after this activity iscompleted can installation of the artificial turf outside of thebuilding can start – the task then takes 12 weeks. Simultaneously,the work on the building can also start once the site iscleared.
The work on the building starts first by excavating and then bypouring of the concrete basement. Each of these activities takes 4weeks to complete. Next comes the construction of the walls (12weeks), followed by constructing the roof (13 weeks). The interiorsare then completed (5 weeks) followed by internal painting (4weeks). However, painting cannot be started until electrical workis completed (4 weeks). The electrical work cannot be started untilthe outside power lines are laid (8 weeks), which needs anadditional activity of getting the permits before it can bestarted. The permit takes 4 weeks. Assume that you would start onthe permits after the excavation activity for the buildingbegins.
Once the roof of the building is erected, work can startsimultaneously on the outside lighting (5 weeks), and on thesignage and other external landscaping (4 weeks). For simplicity,assume you start the project on February 19th and youfollow a 7-day work schedule where each week of an activity’sduration takes 7 days.
Analyze the following questions based on the estimates of theabove activities -
1) When do you complete the project?
Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
- Unlimited Question Access with detailed Answers
- Zin AI - 3 Million Words
- 10 Dall-E 3 Images
- 20 Plot Generations
- Conversation with Dialogue Memory
- No Ads, Ever!
- Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Other questions asked by students
StudyZin's Question Purchase
1 Answer
$0.99
(Save $1 )
One time Pay
- No Ads
- Answer to 1 Question
- Get free Zin AI - 50 Thousand Words per Month
Unlimited
$4.99*
(Save $5 )
Billed Monthly
- No Ads
- Answers to Unlimited Questions
- Get free Zin AI - 3 Million Words per Month
*First month only
Free
$0
- Get this answer for free!
- Sign up now to unlock the answer instantly
You can see the logs in the Dashboard.