Question

Finance

Project M has a cost of $65,125, expected net cash inflows of$13,000 per year for ten years, and a cost of capital of 11%. Whatis the project’s NPV? What is the project’s discounted paybackperiod?

Answer & Explanation Solved by verified expert
3.5 Ratings (655 Votes)
Projects Net Present Value NPV Year Annual Cash Flow Present Value factor at 11 Present Value of Cash Flow 1 13000 0900901 1171171 2 13000 0811622 1055109 3 13000 0731191 950549 4 13000 0658731 856350 5 13000 0593451 771487 6 13000 0534641    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Transcribed Image Text

Project M has a cost of $65,125, expected net cash inflows of$13,000 per year for ten years, and a cost of capital of 11%. Whatis the project’s NPV? What is the project’s discounted paybackperiod?

Other questions asked by students