Project B has an initial cost of $23,956 and its expected net cash flows are...

80.2K

Verified Solution

Question

Accounting

Project B has an initial cost of $23,956 and its expected net cash flows are $6,000 p.a. for the next five years. If the required rate of return is 10%, what is the net present value of the project?

a.

Negative $1950.77

b.

Positive $1211.80

c.

Positive $1950.77

d.

Negative $1211.80