Question

Accounting

Problem 4-18 Contrasting Activity-Based Costing and Conventional Product Costing [LO4-2, LO4-3, LO4-4]
Skip to question
[The following information applies to the questions displayed below.]
Adria Company recently implemented an activity-based costing system. At the beginning of the year, management made the following estimates of cost and activity in the companys five activity cost pools:
Activity Cost Pool Activity
Measure Expected
Overhead Cost Expected
Activity
Labor-related Direct labor-hours $ 34,0008,500 DLHs
Purchase orders Number of orders $ 3,5003,500 orders
Material receipts Number of receipts $ 9,000900 receipts
Relay assembly Number of relays $ 15,0002,500 relays
General factory Machine-hours $ 205,00041,000 MHs
Problem 4-18 Part 2
2. The expected activity for the year was distributed among the companys four products as follows:
Expected Activity
Activity Cost Pool Product A Product B Product C Product D
Labor-related (DLHs)2,5506503,4001,900
Purchase orders (orders)2505001,7501,000
Materials receipts (receipts)3101764140
Relay assembly (relays)2002001,0001,100
General factory (MHs)12,7508,3008,20011,750
Using the ABC data, determine the total amount of overhead cost assigned to each product.

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students