Assume that you are the manager of a shop that assembles powertools. You have just received an order for 60 chain saws, which areto be shipped at the start of week 8. Pertinent information on thesaws is

ItemLead Time (weeks)On HandComponents
Saw215A(2), B(1), C(4)
A110E(3), D(1)
B25D(2), F(3)
C265E(2), D(2)
D120
E110
F230

  
Develop the material requirements plan for component E usinglot-for-lot ordering. (Leave no cells blank - be certain toenter "0" wherever required.)
  

Item: E(3) & E(2) LT = 1 wk.Beg. Inv.12345678
Gross requirements
Scheduled receipts  
Projected on hand
Net requirements
Planned order receipt
Planned order release

Answer & Explanation Solved by verified expert
4.2 Ratings (514 Votes)
Information given is as underProduct structure is shown belowComponent E is required in ComponentA and Component CTo derive the MRP for Component E the MRP of Item SawComponent A and Component C has to be derived first60 units of Chain Saw is to be    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students