please help!! image
image
The following represents a project that should be scheduled using CPM: b. What is the critical path? B-E-G-H A-D-G-H A-C-F-H A-D-F-H c. What is the expected project completion time? Note: Do not round intermediate calculations. Round your answer to 3 decimal places. c. What is the expected project completion time? Note: Do not round intermediate calculations. Round your answer to 3 decimal places. d. What is the probability of completing this project within 22 days? Note: Use Excel's NORM.S.DIST function to find the correct probability for your computed Z volue. Do not round intermediate calculations. Round Z value to 2 decimal places and finol answer to 4 decimal places

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students