PIMS, Inc., has been manufacturing plumbing equipment since 1999. Because of the depressed economic conditions,...

80.2K

Verified Solution

Question

Accounting

PIMS, Inc., has been manufacturing plumbing equipment since 1999. Because of the depressed economic conditions, component parts are assembled in batch runs. At any given time, each level of production has several partially assembled components. Given the following assembly and inventory information, plan the order releases necessary to assemble 400 oil leak valves for period 10.

Production of the valve begins with the base. The base is placed and secured in a housing. Ball bearings are then installed on opposing sides of the base housing. The rear base cover is fitted on and held while the front cover is secured with U-bolts. Next, the anchor assembly is connected. Finally, two sets of brackets are screwed on and the oil leak valve is checked before shipping.image

MASTER FILE ITEM DESCRIPTION LEAD TIME ON ORDER SCHEDULED RECEIPT DATE ON HAND LOT SIZE (MULTIPLES) Oil Leak Valve 1 0 I Brackets 2 30 25 Shield Valve 1 40 1 Anchor assembly 3 50 Period 2 90 25 Sealing Valve 1 10 1 U-bolts 3 105 50 Front cover 2 40 50 Rear cover 2 2 50 Perod 1 0 50 Capping Valve 1 0 1 Ball bearing 3 3 50 Period 1 90 50 Back flush Valve 1 50 1 Base 3 3 25 Period 2 40 25 Base housing 4 25 Period 2 35 25

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students