Percentage-of-completion method. Arshdeep Builders contracted to build a high-rise for $35,000,000. Construction...

50.1K

Verified Solution

Question

Accounting

Percentage-of-completion method.
Arshdeep Builders contracted to build a high-rise for $35,000,000. Construction began in 2018 and is
expected to be completed in 2020. Data for 2018 and 2019 are:
Costs incurred to date Estimated costs to complete
Arshdeep uses the percentage-of-completion method.
Instructions
2018 $4,500,000 18,000,000
2019 $13,000,000
12,000,000
(a) How much gross profit should be reported for 2018? Show your computation.
(b) How much gross profit should be reported for 2019?
(c) Make the journal entry to record the revenue and gross profit for 2019.

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students