PAYBACK PERIOD Project L costs $45,000, its expected cash inflows are $8,000 per year for...

80.2K

Verified Solution

Question

Finance

image
image
PAYBACK PERIOD Project L costs $45,000, its expected cash inflows are $8,000 per year for 7 years, and ts WACC is 10%. What is the project's payback? Round your answer to two decimal places years Project costs $25,000, its expected cash inflows are $5,000 per year for 8 years, and Its WACC is 11%. What is the project's discounted paynach? Round your anger to twe decimal places years

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students