Oriole Construction Company had a contract starting April 2021, to construct a $24300000 building that is expected to be completed in September 2023, at an estimated cost of $22300000. At the end of 2021, the costs to date were $10927000 and the estimated total costs to complete had not changed. The progress billings during 2021 were $5100000 and the cash collected during 2021 was 3230000. Oriole uses the percentage-of-completion method. For the year ended December 31, 2021, Oriole would recognize gross profit on the building of:

a. $899342.

b. $980000.

c. $0.

d. $11373000.

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students