On June 15, 2016, Sanderson Construction entered into a long-term construction contract to build a...

60.1K

Verified Solution

Question

Accounting

On June 15, 2016, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $390 million. The expected completion date is April 1, 2018, just in time for the 2018 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions):

2016 2017 2018

Costs incurred during the year $60 $130 $70

Estimated costs to complete as of December 31 190 60 ---

Required:

Determine the amount of revenue, cost, and gross profit or loss to be recognized in each of the three years under IFRS, assuming that using the percentage-of-completion method is not appropriate. (Enter your answers in millions.)

2016 2017 2018

Revenue ? ? ?

Cost 60 130 70

Gross Profit (loss) to be recognized: ? ? ?

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students