On June 15, 2016, Sanderson Construction entered into a long-term construction contract to build a...

90.2K

Verified Solution

Question

Accounting

On June 15, 2016, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $220 million. The expected completion date is April 1, 2018, just in time for the 2018 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are asfollows ($ in millions):

2016

Costs incurred during the year $ 40

Estimated costs to complete as of December 31 $120

2017

Costs incurred during the year $80

Estimated costs to complete as of December 31 $60

2018

Costs incurred during the year $50

Estimated costs to complete as of December 31 -0-

1. How much revenue and gross profit will Sanderson report in its 2016, 2017, and 2018 income statements

related to this contract assuming Sanderson recognizes revenue over time according to percentage of

completion?

2. How much revenue and gross profit will Sanderson report in its 2016, 2017, and 2018 income statements

related to this contract assuming this project does not qualify for revenue recognition over time?

3. Suppose the estimated costs to complete at the end of 2017 are $80 million instead of $60 million. Determine

the amount of revenue and gross profit or loss to be recognized in 2017 assuming Sanderson recognizes revenue

over time according to percentage of completion.

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students